2940 Street Improvements Sunset DriveORDINANCE NUT,.1BER 2940.
Salina Dailv Union February 01- 1924
one piece combination cement curb and gutters,—said combined curb
and gutter shall be comprised of a curb six (6) inches thick at the
top and six and one-half (62) inches thick at the throat, with
gutter twenty-four (24) inches viide,, six (6) inches thick at the
throat and seven (7) inches thick next to the pavement.
An Ordinance specifying and selecting the paving material to be
used and letting a contract for the curbing, guttering, ex-
cavating, grading and paving of Sunset Drive in the City of
SalinaKansas from the west line 3?Wi_n_t_h=treet thence
I
west to Highland Circle in said City.
BE IT ORDAINED by the Board of Commissioners of the City of
Salina, Kansas:
Section 1. That it is hereby determined that Sunset Drive
in the City of Salina, Kansas from the west line of Ninth Street
thence west to Highland Circle shall be paved with one course vitri-
fied vertical fiber plain wire out bricks not less than three (3)
inches deep, with asphalt filler laid on a foundation of five (5)
inches in depth of Portland Cement Concrete base with one (1) inch
sand cushion, such pavement within the limits above defined to be
thirty-four (34) feet in width excluding curb and gutter.
Section 2. That it is hereby determined that -Sunset Drive
in the City of Salina, Kansas from the west line of Ninth Street
thence west to Highland Circle shall be curbed and guttered with
one piece combination cement curb and gutters,—said combined curb
and gutter shall be comprised of a curb six (6) inches thick at the
top and six and one-half (62) inches thick at the throat, with
gutter twenty-four (24) inches viide,, six (6) inches thick at the
throat and seven (7) inches thick next to the pavement.
Section 3. All excav ating, filling and rolling necessary for
the proper construction of such improvements shall be done and all
of such improvements shall be made and done in strict conformity to
and in compliance with the plans and specifica"d ons heretofore made
by the City Engineer of Salina, Kansas and now on file with the City
Clerk of said City, which plans and specifications are hereby incor-
porated in and made a part hereof in all respects as fully and com-
pletely as though written out at length herein; which said plans
and specificat ons are hereby adopted as and for the plans and spe-
cifications are hereby adopted as and for the plans and specificaticn
and improvements.
of such work
Section 4. -That a contract is hereby awarded to C.P.Barring-
ton for the paving, curbing, guttering, excavating and filling the
above mentioned street in the limits aforesaid vith the materials
hereinbefore specified, for the paving actually laid and put in
placellfor the labor actually performed and the materials actually
furnished at the following prices: For excavating and grading
One and No/100(01.00) Dollars per cubic yard; for Portland Cement
Concrete combined curb and gutter Ninety cents (90�) per lineal
foot; and for paving actually laid and put in place Three & 23/100
($3.23) per square yard. All of said work shall be paid for
according to the measurement made by the City Engineer of the
City of alina. It is hereby determined and found that the prices
to be paid for the improvements as aforesaid is less than the
estimated prices of each and all of said improvements as now on
file with the City Clerk of the City of Salina, Kansas.
Section 5+ -Such contract is awarded upon the express condition
that such work and improvements shall be dune in strict accordance
with and in compliance with the plans and specifications of the
City Engineer therefor, which plans and specifications are hereby
made a part of this ordinance and of the contract awarded, and upon
further conditions among others that the person to whom said contract
is awarded shall furnish to the City of Salina a surety company bond
in the approximate sun of the cost of such improvements guarantee-
ing the prompt, proper and workmanlike construction of all the
same together with a surety company bond guaranteeing such pavement
against all defects in material and workmanship for a period of
five (5) Fears from the date of its completion and- acceptance by
said City; and said contract is awarded upon a further condition
that said C. P. Barrington shall furnish to the City of Salina a
good and sufficient surery company bond guaranteei
STATE OF KANSAS
COUNTY OF SALINE
I Chas. E. Banker -1�-ansas
City Clerk of the City of Salina
do hereby certify that the above and foregoing is a true and cor-
rect copy of Ordinance Number 2940 passed and approved by the
Board of Commissioners, February 18th., 1924; and a record of the
T
vote on its final adoption is found on Page -Iof Journal
Number 104P Said Ordinance was published in The Salina Daily
Union February �-.1924.
D
F-�
(Published in The Salina Daily Union,'-I4� °a te 1924)
ORDINANCE NO. 2940
An brdinance specifying and selecting the paving material to'be
used and letting a contract for the curbing, guttering, ex-
cavating, grading and paving of Sunset Drive in the City of
Salina, Kansas from the west line of Ninth street thence
west to Highland Circle in said City.
BE IT ORDAINED by the Board of Commissioners of the City of
Salina, Kansas:
Section 1. That it is hereby determined that Sunset Drive
in the City of Salina; Kansas from the west line of ninth Street thence
west to Highland Circle shall be paved with one course vitrified
vertical fiber plain wire out brick, not less than three (3) inches
deep, with asphalt filler laid on a foundation of five (5) inches
in depth of Eorbland Cement Concrete base with one (1) inch sand
cushion, such pavement within the limits above defined to be
thirty-four (34) feet in width excluding curb and gutter.
Section 2. That it is hereby determined that Sunset Drive
in the City of Salina, Kansas from the west line of Ninth Street thence
west to Highland Circle shall be curbed and guttered with one piece
combination cement curb and gutter, said combined curb and gutter
shall be comprised of a curb six (6) inches thick at the top and
six and one-half (62) inches thick at the throat, with gutter
twenty-four (24) inches wide, six (6) inches thick at the throat
and seven (7) inches thick next to the pavement.
Section 3. All excavating, filling and rolling necessary for
the proper construction of such improvements shall be done and all
of such improvements shall be made and done in strict conformity to
and in compliance with the plans and _specifications heretofore made
by the City Engineer of Salina, Kansas and now on file with the City
Clerk of said City, which plans and specifications are hereby incor-
porated in and made a part hereof in all respects as fully and com-
pletely as though written out at length herein; which said plans and
specifications are hereby adopted as and for the plans and specifi-
cations of such work and improvements.
�1
Section 4. That a contract is hereby awarded to C. P. Barring-
ton for the paving, curbing, guttering, excavating and filling the
above mentioned street in the limits aforesaid with the materials
hereinbefore specified, for the paving actually laid and put in
place, for the labor actually performed and the materials actually
furnished at the following prices: For excavating and grading
One and No/100 ($1.00) Dollars per cubic yard; for Portland Cement
Concrete combined curb and gutter Ninety cents (90/) per lineal
foot; and for paving actually laid and put in place Three and 23/100
($3.23) Dollars per square yard. A11 of said work shall be paid for
according to the measurement made by the City Engineer of the City
of Salina. It is hereby determined and found that the prices to be
paid for the improvements as aforesaid is less than the estimated
prices of each and all of said improvements as now on file with the
City Clerk of the City of Salina, Kansas.
Section 5. Such contract is awarded upon the express condition
that such work and improvements shall be done in strict accordance
with and in compliance with the plans and specifications of the
City Engineer therefor, which plans and specifications are hereby
made a part of this ordinance and of the contract awarded, and upon
further conditions among others that the person to whom said contract
is awarded shall furnish to the City of Salina a surety company bond
in the approximate sum of the cost of such improvements guaranteeing
the prompt, proper and workmanlike construction of all the same
together with a surety company bond guaranteeing such pavement against
all defects in material and worlananship for a period of five (5)
years from the date of its completion and acceptance by said City;
and said contract is awarded upon a further condition that said
C. P. Barrington shall furnish the City of Salina a good and sufficient
surety company bond guaranteeing said curb and gutter against all
defects in material and worlananship for a period of two (2) years
from the date of its completion and acceptance of such work by the
City; together with a good and sufficient surety company bond running
to the State of Kansas in an amount approximately equal to the
contract price of said improvements and conditioned that said
C. P. Barrington shall pay all indebtedness for labor and material
furnished in making the improvements provided for herein.
Section 6. The Board of Commissioners of the City of Salina
are hereby authorized to make and enter into on behalf of said
City allviritten agreements necessary in order to secure the
construction of the improvements herein provided for.
Section 7. This ordinance shall take effect and be in full
force from and after its publication once in the official City
paper.
Introduced for first reading, February 11th, 1924.
Passed and approved --------- February 18th, 1924
6 yor
Attest:
City lerk.