06-12-1928 Minutes'A4
COMMISSIONERS PROCEEDINGS, REGULAR MEETING.
COMMISSIONERS ROOM,
SALINA, KANSAS.
JUNE 12th, 1928.
Adjourned meeting of the Board of Commissioners, June
12th, 1928. Meeting was called to order by Mayor Helvering,
the roll was called and Commissioners Helvering, Campbell and
Dodds and City Attorney Norris responded.
Commissioner Dodds moved that the contract for paving
301 slab on North Street from the east Line of Twelfth Street
to the west line of Whittredge Street be awarded to L. W. Rex -
road, as per his bid submitted, and that the Mayor be authorized
to sign contract for said improvement. Motion carried.
Commissioner Campbell moved that the contract for the
curbing, guttering and paving of North. Street from the west
line of Ninth Street to the east line of elfth Street be
awarded to H. J. Taylor Construction Company for 22 inch brick
on 6'r concrete base; also that the contrac t for curbing and
guttering of north side of Euclid Avenue from the west line of
Fifth Street to the east line of Ninth Street be awarded to
H. J. Taylor Construction Company as per his bid submitted, and
that the Mayor be authorized to sign contract for said improve-
ments. Motion carried.
An ordinance was introduced for first reading entitled;
"An ordinance ratifying and confirming a contract for the ex-
cavating, grading and paving of North Street from the east
line of Twelfth Street to the city limits at the intersection of
North 6treet with the Union PacificrrRailroad right-of-way being
the west line of Whittredge Street.
On motion of Commissioner Dodds same was referred to the
Board of Commissioners.
An ordinance was introduced for first reading entitled:
"An ordinance confirming and ratifying a contract for the
improvement of certain streets in the City of Salina, Kansas,
and providing for the issuance of temporary notes to pay the
cost thereof, pending the issuance and sale of bonds for the
payment of the cost thereof."
On motion of Commissioner Campbell same was referred to
the Board of Commissioners.
Commissioner Campbell moved that the contract for Storm
Sewers 7-A and 8-A, be awarded to C. T. Snyder as per his bid
submitted, said job to be completed on or before the 15th day
of July, 1928, and a penalty of 425.00 per day for each and
every day after the expiration of the time limit, until such
work is completed., and that the Mayor be authorized to sign
contract for said improvements. Motion carried.
Commissioner Campbell moved that the contract for lateral
sanitary sewers No. 141 and 142, be awarded to C. T. Snyder as
per his bid submitted, said job to be completed on or before
the 25th day of July, 1928, and a penalty of $25.00 per day for
each and every day after the expiration of the time limit until
such work is completed, and that the Mayor be authorized to sign
contract for said improvements. Motion carried.
An ordinance was introduced for first reading entitled:
"An ordinance ratifying and confirming a contract for the
building and construction of certain storm sewers in the City
of -alina described as Storm ewers 7-A and 8-A and providing
for -the issuance of temporary notes to pay the cost thereof,
pending the issuance and sale of bonds for the payment of such
cost*'r
On motion of Commissioner Dodds same was referred to the
Board of Commissioners.
An ordinance was introduced for first reading entitled:
"An ordinance ratifying and confirming a contract for the
building and construction of certain lateral sanitary sewers in
Leteral Sewer Districts No. 141 and 142 in the City of Salina
and providing for the issuance of temporary notes to pay the
cost thereof pending the issuance and sale of bonds for the
payment of such cost.
47P
On motion of Commissioner Campbell same was referred to the
Board of Commissioners.
City Clerk was instructed to publish necessary Weed
Notice, notifying property owners to cut their weeds according to
law.
On motion of Commissioner Dodds, meeting adjourned.
i
City Clerk.