13-6966 2013-2017 Capital Improvement ProgramRESOLUTION NUMBER 13-6966 A RESOLUTION ADOPTING THE 2013-2017 CAPITAL IMPROVEMENT PROGRAM FOR THE CITY OF SALINA, KANSAS. WHEREAS, the City of Salina has established a Capital Improvement Program Policy as a component of its Financial Policies Document; and s g WHEREAS, the Policy includes establishment of a five-year Capital Improvement Program (C.I.P.) to guide decision making on public improvements and expenditures; and WHEREAS, the City Commission has completed its annual review of capital improvement planning. SO NOW THEREFORE BE IT RESOLVED by the Governing Body of the City of Salina, Kansas: Section 1. That the 2013-2017 Capital Improvement Program is hereby adopted. Section 2. That no project shall be initiated unless said project is contained in the adopted Capital Improvement Program or otherwise authorized by the Governing Body. Section 3. That the Capital Improvement Program and this resolution may be amended from time -to -time as deemed appropriate by the Governing Body. Section 4. That this resolution shall be in full force and effect from and after its adoption. Adopted by the Board of Commissioners and signed by the Mayor this 7th day of January, 2013. Norman M. Jennings, Mayor (SEAL) L T: /1 Lieu Ann Elsey, CMC, City v DEPARTMENT OF FINANCE City0f TELEPHONE (785) 309-5735 ANDADMINISTRAfION FAX (785) 309-5738 Rodney Franz, Director TDD (785) 309-5747 300 West Ash, P.O. Box 736 E-MAIL rod.franz@salina.org Salina, Kansas 67402-0736 Salina Website: www.salina-ks.gov To: Salina City Commission Transmitted herewith is the preliminary 2013 through 2017 Major Capital Improvements Program. Major capital projects and purchases are scheduled by the year in which construction is anticipated to begin. Projects for which funding is not available within the project period, or for which the project scope has not been sufficiently defined are shown in the "Identified but Unfunded" and "Projects for Future Review" sections. Information for each project includes the project title and brief description or need, the contemplated funding source and timing, and the estimated cost of the project. The "sub-CIP" (annual cash financed acquisitions and projects) for 2013 is included at the back of the document. The sub-CIP for 2013 includes the following items: Class Budget all funds Request Total Buildings and Facilities $ 290,000 $ 255,000 Park Improvements $ 130,000 $ 130,000 Streets, Traffic, and Sidewalks $ 2,747,396 $ 2,747,000 Vehicles and Equipment $ 1,539,960 $ 1,476,260 System Enhancements $ 1,700,000 $ 1,700,000 1 $ 5,630,000 Major projects scheduled by year are as follows: Year Amount 2013 $ 27,990,981 2014 $ 10,616,000 2015 $ 27,281,000 2016 $ 7,531,000 2017 1 $ 5,630,000 213 Attachment "C" shows the fiscal impact of the Capital Improvements Program on the Bond and Interest Fund. The projected mill levy required to financed program are as follows: Year Levy Rate 2012 Current Year 5.95 2013 5.96 2014 5.95 2015 5.95 2016 5.95 2017 5.95 2018 5.35 As can be seen from the table, the projected mill levy is relatively stable. As a matter of reference, one (1) mill supports about a $4.5 million improvement over a 15 year term. The other major funding source for projects in the Capital Improvements Program is the Water and Wastewater Fund. Water and Wastewater rates are set at levels that will support the proposed program through the project period, including debt service, set -asides for cash capital and capital reserve accounts. Table of Contents: 2013 Project Listing................................................................................. 215 2014 Project Listing................................................................................. 218 2015 Project Listing................................................................................. 220 2016 Project Listing................................................................................. 222 2017 Project Listing.................................................................................. 223 Identified but Unfunded Projects................................................................. 224 Projects for Future Review........................................................................ 225 General Debt Financial Pro-forma................................................................. 229 SalesTax Pro-forma.................................................................................. 230 2012 Sub-CIP......................................................................................... Following 231 214 2013 Proiects Waterline Improvements The Water Distribution System engineering analysis identified a significant portion of the system in which proper functioning with regard to fire flow and consistently high water quality is in peril do to the aging condition and occlusion of water lines. Approximately 228 miles of line is of cast iron construction and more than 40 years old. This line is subject to occlusion from mineral deposits which reduces flow. While the product is disinfected and safe to consume, the water quality is undesirable water quality due to discoloration, and taste and odor issues. This project will replace approximately 40,000 feet (8 miles) of waterline per year. At this rate of replacement, it will take 28 years to replace the cast iron stock with PVC line Project Cost: $4,000,000 annually. This project will be financed with State Revolving Loan funds. Annual payments are estimated at $268,883 over 20 years. Wastewater Plant Preliminary Design Fhe Salina Wastewater Plant is due for an upgrade to meet EPA and KDHE permitting requirements. The project will convert anaerobic digestion to an aerobic treatment process utilizing biological nutrient removal. The existing primary and secondary treatment systems will be removed, and new facilities substituted. This provides for the preliminary design of the facility in preparation for construction in 2015. Project Cost: $810,000. The source of funding will be revenue bonds payable over 20 years. The annual payment will be about $52,000 per year. First payment will be in 2014. Wayfinding Continuation and completion of the Wayfinding project began in 2009. Project Cost: $200,000. This is to be provided by the Special Sales Tax proceeds. Flood Control Levee Improvements for Certification One of the results of the Hurricane Katrina disaster was a requirement by FEMA that all flood control levy's in the United States undergo a "recertification" procedure. That procedure is a two step process: First, an engineering study to identify potential deficiencies in levy design, construction, or maintenance, and, second, remediation of those deficiencies. The preliminary engineering study by AMEC has determined that the flood control levee elevation needs to be raised in two locations—south of State Street and East of Ninth Street. In addition, we will need to perform some riprap and erosion/scour repairs. Project Cost: $375,000, including $25,000 for Engineering. Source: Sales Tax Hike Bike Trail (2013 - 2017) Complete annual segments of the trail improvement. Project Cost: $25,000. Sales Tax. 215 BiCentennial Center Improvements: This is a multi -faceted project incorporating improvements to both the interior and exterior of the building. This project includes concession stand improvements, Arena Improvements, HVAC improvements/replacement, restrooms, floor coverings, and kitchen/catering improvements. Much of this facility is original construction, from the late 1970's. This project has been identified as appropriate for aesthetic enhancements under the City's Community Art and Design policy, which provides for up to 5% of the project cost to be allocated for that purpose. Project Cost: Estimate from Global Spectrum is $8.7 million. Source will be General Obligation Bonds, with a 20 year term. Annual payment is $550,000. Payments from 2015 through 2019 scheduled out of Sales Tax fund and thereafter from the Bond and Interest Fund. Gateway Signage: Install monument gateway sign Southwest quadrant of the 1-70 and North Ninth Street Interchange Project Cost: $75,000 Sales Tax. Cloud and Ninth Street Intersection Improvements Realign travel lanes at intersection to improve traffic flows. Project Cost: $650,000 Source: General Obligation Bonds/KDOT Grant $350,000 Annual Payment: $51,346 Downtown Lighting Replace the decorative lights throughout the downtown district. Remove High Bay street lights, expand coverage area. New poles, LED lighting, removal of separate overhead lighting system. Project Cost: $3,118,981. Net after projected project savings: $1,651,047 General Obligation Bonds; 15 year term. T -note issued 2013, bonds 2014, first bond payment 2015. Annual payment projected at $239,424. 216 Replace Management Software Systems. City Management depends on a variety of business computing systems to help them accomplish administrative tasks such as Personnel Management, Financial Management, and Financial Reporting. The software currently used for these tasks was installed in 1992, is based on very old technology, and is inadequate for many of the tasks desired. The current vendor (New World Systems) has released software designed to run as a networked system (dot.net), and has stopped marketing the old style software. In the two years since the dot.net package was made available, more than 125 out of 225 customers have switched or otherwise upgraded their systems. While New World still expresses a commitment to support the old style packages, as the number of users declines, that will become more and more expensive. Based on the experience of the last two years, we anticipate that support will become prohibitively expensive, if available at all in the next 3-5 years. Project Cost: $600,000 Financed by lease purchase from operational funds. 5 year term. Annual payment of $130,000. Sales Tax Downtown Well Field Improvements This project will increase the supply capacity of the Downtown Well Field from 10 MGD to 13 MGD. The project includes the re -drilling of four wells, replacement of approximately 4,900 feet of undersized piping, and increases the capacity of the air stripping facilities at the Water Treatment Plant. The project estimate is $4,300,000 tobe financed through the State Revolving Loan Fund. Annual payments will be about $290,000, with the first payment due in 2015. KWO Water Security District This project will protect surface water supplies available from the Smoky Hill River. The cost is estimated at $2,500,000, to be financed with Revenue bonds over 20 years. Annual costs are estimated at $168,000, beginning in 2014 Wastewater Force Main Projects: These were construction of a number of smaller facilities, largely rebuilding and rehabilitation of pump stations and associated force mains and other facilities. Remaining portions of the project to be completed in 2013 are the replacement of the force main for Pump Station # 44, abandon Pump Station # 9 and install gravity line to Pump Station # 49. Project Cost (remaining): $500,000. Financed with GO Bonds with pledged revenue. Bonds issued in 2013, with first payments due in 2014. Annual Cost is about $40,000 per year Southeast Salina Wastewater Extension: Construction of a collector system for South East Salina to serve the Magnolia and Markley Road Vicinity. Project Cost: $1,650,000. Financed with GO Bonds with pledged revenue. Bonds issued in 2013, with first payments due in 2014. Annual Cost is about $110,000 per year 217 2014 Proiects Waterline Improvements The Water Distribution System engineering analysis identified a significant portion of the system in which proper functioning with regard to fire flow and consistently high water quality is in peril do to the aging condition and occlusion of water lines. Approximately 228 miles of line is of cast iron construction and more than 40 years old. This line is subject to occlusion from mineral deposits which reduces flow. While the product is disinfected and safe to consume, the water quality is undesirable water quality due to discoloration, and taste and odor issues. This project will replace approximately 40,000 feet (8 miles) of waterline per year. At this rate of replacement, it will take 28 years to replace the cast iron stock with PVC line Project Cost: $4,000,000 annually. This project will be financed through the issuance of 20 year revenue bonds each year. Fire Engine Replacement Replace fire pumper (a 1991 Pierce) that will be nearing the end of it's service life. Project Cost: $500,000. Source: Sales Tax. Hike Bike Trail (2013 - 2017) Complete annual segments of the trail improvement. Project Cost: $50,000. Sales Tax Oakdale Park Parking Lot Pavement Repair and Resurface Parking Lot Project Cost: $107,000 Sales Tax. Iron Avenue Reconstruction. This project will provide for improvements and major maintenance to Iron Avenue from Front Street to Ohio Street. Pavement cores indicate thin asphalt over brick in the outside lanes with thick asphalt over concrete in the center lane. Project will include removal and replacement of pavement on the outside lanes, milling and inlaying on the center lane, and minimal curb and gutter replacement Project Cost is $994,000. Source: General Obligation Bonds. 10 year term. Annual Payment is $78,520 Gateway Signage: Install monument gateway sign Southwest quadrant of the Crawford/Centennial/1-135 Interchange Project Cost: $75,000 Sales Tax. Police Department Boiler Replacement The existing boiler was installed in 1967 and has a 60% efficiency rating. The unit has exceeded its projected life expectancy. The old unit will be replaced with a 90% energy efficient unit. Project Cost: $90,000 Sales Tax Fire Headquarters Remodel, Phase II The second phase of this project is estimated at $1,400,000. This project will improve the living conditions of fire personnel, the efficiency of the administration, the movement of fire apparatus in and out of the station, and the safety of fire personnel in providing adequate facilities to decontaminate ambulances and medical equipment. Project Cost: $1,400,000 Source: General Obligation Bonds Annual Payment: $110,592 218 Landfill Cell #6 Construction of Cell 6. This project includes construction of a leachate collection pond to serve future cells. Scheduled for opening in 2015, construction in 2014. Estimated Cost $1,800,000. Source of Funds will be General Obligation Bonds, to be paid from Landfill Revenues. Clean and rehabilitate North Lime Drying Lagoon This project includes removal and disposal of approximately 180,000 cubic yards of material and repairing 300 feet of damaged dike. This lagoon has been in operation for 33 years, and is approaching capacity. This will be the first cleanout. Project Cost: $1,600,000 Source: Revenue Bonds Annual Payment: $168,000 219 2015 Projects: Waterline Improvements The Water Distribution System engineering analysis identified a significant portion of the system in which proper functioning with regard to fire flow and consistently high water quality is in peril do to the aging condition and occlusion of water lines. Approximately 228 miles of line is of cast iron construction and more than 40 years old. This line is subject to occlusion from mineral deposits which reduces flow. While the product is disinfected and safe to consume, the water quality is undesirable water quality due to discoloration, and taste and odor issues. This project will replace approximately 40,000 feet (8 miles) of waterline per year. At this rate of replacement, it will take 28 years to replace the cast iron stock with PVC line Project Cost: $4,000,000 annually. This project will be financed through the issuance of 20 year revenue bonds each year. Wastewater Treatment Plant Improvements Improvements are needed to our Wastewater Treatment processes in order to comply with the Kansas Department of Health and Environment Surface Water Nutrient Reduction Plan by 2020. The project will convert anaerobic digestion to an aerobic treatment process utilizing biological nutrient removal. The existing primary and secondary treatment systems will be removed, and new facilities substituted. Preliminary Design is scheduled for 2013. Construction is anticipated to begin in 2015 or 2016, and will take several years to complete. Project Cost: The preliminary cost estimate for this project is on the order of $20,000,000. Of this amount, $8,000,000 is scheduled to come from the Capital Reserve Fund, and $12,000,000 financed by revenues bonds. Annual payment will be on the order of $900,000 per year for 20 years. First payment is scheduled for 2016. South Well field Design The Raw Water Supply Study identified a number of improvements to the South Wellfield and plant that will be necessary to insure a high quality reliable water supply through 2060. This project will incorporate a number of improvements to existing facilities, as well as new facilities that may be required. The design phase provides for a detailed engineering design of facilities necessary, and sound cost estimates. The construction phase of this project is currently located in the "Further Review" section of the Capital Improvements Program. Project cost: The design of the project is anticipated to cost $1,350,000. Financed with Revenue Bonds in 2015. Annual payments are projected to be approximately $108,000 per year for 20 years. The first payment will be due in 2016. Country Club Road Reconstruction This project includes major pavement maintenance on Country Club Road from Marymount Road to Eastborough Road and on Marymount Road from Iron Street to Country Club Road. The project will include removal and replacement of the existing pavement; repair and/or addition of curb and gutter, underground storm sewers and a 5' pedestrian/bicycle path. Project Cost: $1,516,000 General Obligation Bonds. Ten year term, annual payment of $119,756 for 20 years. Hike Bike Trail (2013 - 2017) Complete annual segments of the trail improvement. $50,000. Sales Tax. Gateway Signage: Install monument gateway sign at the Southwest quadrant of the Crawford/Centennial/1-135 Interchange Project Cost: $75,000 Sales Tax. 220 Replace Lighting for East Crawford Recreation Area, Fields 1 through 4 The current lighting at the East Crawford recreation area is more than 28 years old and does not meet the minimum industry standards for illumination. The recommended illumination for these fields is 30 horizontal foot candles in the infield and 20 horizontal foot candles in the outfield. Current illumination levels are 17 horizontal foot candles in the infield and less than 10 in the outfield. The age of the fixtures is also resulting in increasing maintenance costs. In the last year, this has been more than $15,000. The new light fixtures require less than half of the energy as the current fixtures. In addition, the product cost for a new fixture includes a 25 year warranty on maintenance, labor and materials. Project Cost: $365,000 Source: Sales Tax Centennial Road from Jumper to South City Limits. This project will provide for the completion of Centennial Road Improvements through the length of the Airport Industrial Park. This segment is listed as an impact street in the comprehensive plan. Project includes at least removal and replacement of existing pavement, addition of curb and gutter, addition of underground storm sewers, extension of reinforced box culverts, and 5' sidewalks on each side of Centennial road. This segment of roadway has deteriorated beyond where additional maintenance is cost efficient Project Cost is $887,000. Financed by General Obligation Bonds, 15 years. Annual payment is $70,068 221 2016 Projects Waterline Improvements The Water Distribution System engineering analysis identified a significant portion of the system in which proper functioning with regard to fire flow and consistently high water quality is in peril do to the aging condition and occlusion of water lines. Approximately 228 miles of line is of cast iron construction and more than 40 years old. This line is subject to occlusion from mineral deposits which reduces flow. While the product is disinfected and safe to consume, the water quality is undesirable water quality due to discoloration, and taste and odor issues. This project will replace approximately 40,000 feet (8 miles) of waterline per year. At this rate of replacement, it will take 28 years to replace the cast iron stock with PVC line Project Cost: $4,000,000 annually. This project will be financed through the issuance of 20 year revenue bonds each year. Hike Bike Trail (2013 - 2017) Complete annual segments of the trail improvement. Anticipate a cost of $50,000 per year. Sales Tax. Widen North Ohio Street from North Street to Elm Street This project will make the construction of this short stretch of Ohio Street consistent with those section to the North and the South. This street is an impact street in the Comprehensive Plan. The project will include removal, replacement and widening of the existing pavement, addition of curb and gutter, underground storm sewers, and 5' sidewalks on each side. Project Cost: $1,170,000 Source: Bonds 15 year term. Annual Payment $92,421 Police Department HVAC Chiller The current chiller was installed in 1989. Over the last two years, it has required $20,000 in repairs. Replacement will minimize ongoing repair costs, and improve energy efficiency by 10% Project Cost: $90,000 Source: Sales Tax Iowa and Gypsum River Bank Stabilization The Corps of Engineers is performing a feasibility study. Construction cost will be split with the Corps. The City will be responsible for 35% of the cost. Project Cost (City): $335,000 Source: Sales Tax Clean and rehabilitate South Lime Drying Lagoon This project includes removal and disposal of approximately 180,000 cubic yards of material and repairing 300 feet of damaged dike. This lagoon has been in operation for 33 years, and is approaching capacity. This will be the second cleanout. Project Cost: $1,600,000 Source: Revenue Bonds Annual Payment: $168,000 222 2017 Projects Waterline Improvements The Water Distribution System engineering analysis identified a significant portion of the system in which proper functioning with regard to fire flow and consistently high water quality is in peril do to the aging condition and occlusion of water lines. Approximately 228 miles of line is of cast iron construction and more than 40 years old. This line is subject to occlusion from mineral deposits which reduces flow. While the product is disinfected and safe to consume, the water quality is undesirable water quality due to discoloration, and taste and odor issues. This project will replace approximately 40,000 feet (8 miles) of waterline per year. At this rate of replacement, it will take 28 years to replace the cast iron stock with PVC line Project Cost: $4,000,000 annually. This project will be financed through the issuance of 20 year revenue bonds each year. Hike Bike Trail (2013 - 2017) Complete annual segments of the trail improvement. Project Cost: $50,000 per year. Source: Sales Tax. Police Department Electrical Service Upgrade Electrical Service in the building is at capacity. All additional service upgrades needed by the Police Department require additional power. Project Cost: $110,000 Source: Sales Tax Replace Lighting for East Crawford Recreation Area, Matson Field and Dean Evans The current lighting at the East Crawford recreation area is more than 28 years old and does not meet the minimum industry standards for illumination. The recommended illumination for these fields is 30 horizontal foot candles in the infield and 20 horizontal foot candles in the outfield. Current illumination levels are 17 horizontal foot candles in the infield and less than 10 in the outfield. The age of the fixtures is also resulting in increasing maintenance costs. In the last year, this has been more than $15,000. The new light fixtures require less than half of the energy as the current fixtures. In addition, the product cost for a new fixture includes a 25 year warranty on maintenance, labor and materials. Project Cost: $300,000 Source: Sales Tax 223 Identified but Unfunded Projects Identified but unfunded projects are those for which a need and project scope has been identified, but which have no funding mechanism or time frame assigned. Flood Control Levee Culvert Repairs: Video investigations have determined that seven culvert pipes are cracked or deteriorated to a level where repairs are necessary. Cost will be $50,000. Scheduling is dependant of funding. North Flood Control Pump Station Study the practicality/need of upgrading the two pumps at the North pump station to a larger size. Cost of the study is estimated at $30,000. Study Laurie Pond Expansion Study the need to expand Laurie Pond. The pond design incorporated the concept of using "street flooding" as temporary storage. Study Cost: $30,000. Friendship Center Parking: Mill and inlay the parking lot with 2" of new asphalt. $41,100. Unknown Funding Source. Sunset Park Restrooms Replace the existing depression era restrooms in Sunset Park with modern, heated, handicapped accessible facilities. This project has been identified as appropriate for aesthetic enhancements under the City's Community Art and Design policy, which provides for up to 5% of the project cost to be allocated for that purpose. Project Cost: $242,000. Oakdale Park Restrooms Replace the existing depression era restrooms in Oakdale Park with one modern, heated, handicapped accessible facility. This project has been identified as appropriate for aesthetic enhancements under the City's Community Art and Design policy, which provides for up to 5% of the project cost to be allocated for that purpose. Project Cost: $172,000. Closure, Landfill Cells 3 and 4 Final closure on Landfill Cells 3 and 4, pursuant to Subtitle D regulations. Project Cost: $1,600,000, to be financed over an 8 year period. Annual payments will be approximately $240,000 per year, payable from Solid Waste fees. 224 Proiects for Future Review Projects for further review are those projects that have been identified as potential needs, but which do not yet have a well defined scope or financing sources identified. Replace irrigation system at Municipal Golf Course The original irrigation system was installed in 1969 and is now 43 years old. Many of the main lines are made with asbestos, making repairs dangerous and difficult to manage. The configuration of the system does not allow for efficient watering. The configuration and types of the sprinkler heads used on the greens makes hand watering necessary during the summer months. A modern system would allow isolation of parts of the system during repairs. That is currently not possible, meaning the system must be drained, which consumes time and resources, and puts turf at risk. Project Cost: $775,000 Unknown Source of funding. Indian Rock Lodge Replacement The existing Indian Rock Lodge was at one time an open air shelter that has been enclosed to permit year around use. It is the second most used facility in the City, and due in part to it not having been designed as an enclosed structure, it is in deteriorating condition. IT does not include a kitchen or restroom facilities, The replacement building would be a multi -use building with kitchen, restrooms, and a large meeting area. This project has been identified as appropriate for aesthetic enhancements under the City's Community Art and Design policy, which provides for up to 5% of the project cost to be allocated for that purpose. Project Cost $506,000 Bonds; Sales Tax Levee Trail Northwest Add an Ag -Lime surface to the levee from Thomas Park to North Street, a distance of 2.9 miles. This would connect Thomas Park to the levee trail system and would add 2.9 miles. This would make it possible to walk or ride a bike from the north side of town to the south side town, a distance of 7.25 miles. This project has been identified as appropriate for aesthetic enhancements under the City's Community Art and Design policy, which provides for up to 5% of the project cost to be allocated for that purpose. Project Cost: $150,000 Unknown Source Levee Trail Northwest Add ag-lime surface on levee from Thomas Park to West Crawford, a distance of 3.4 miles. This project would complete the levee trail system. The system would encircle most of the City, and would connect West Cloud Street to South Ohio at Schilling Road. This project has been identified as appropriate for aesthetic enhancements under the City's Community Art and Design policy, which provides for up to 5% of the project cost to be allocated for that purpose. Project Cost: $180,000 Unknown Source Magnolia Multi -use Trail This is a ten foot (10') wide concrete multi -use trail constructed on the south side of Magnolia from South 9th Street to South Ohio Street. This mile long trail would connect Jerry Ivey Park, South High School and the businesses along South 9th Street Project Cost: $ 325,000 Unknown Source 225 East Salina Master Plan Improvements This project would provide public facilities to serve the area North of Crawford Street to Country Club Road and east of the City Limits to Holmes Road. The estimated cost of the improvements is $5,500,000. These would be funded in part by Special Assessments to benefiting property, but there would also be significant agricultural deferrals, cost recoveries, and other at -large components to the project. Smoky Hill River Renewal: Renewal of the old Smoky Hill River channel, clearing and sloping the channel, hike/bike paths, and ancillary improvements. This project has been identified as appropriate for aesthetic enhancements under the City's Community Art and Design policy, which provides for up to 5% of the project cost to be allocated for that purpose. Projected Cost $27,700,000 Holmes Road, Magnolia to Country Club This consists of improvements to Holmes Road from Magnolia to Country Club Road, complimenting the East Salina Master Plan improvements. Cost is estimated at approximately $2,500,000, to be funded through Special Assessments and General Obligations. Markley Road from Old Airport to Magnolia Improve this segment of road to an urban standard. $2,000,000. Funding source will likely be General Obligation Bonds Complete Cedar Ridge Drive to Markley Road This length of roadway (about 1,050 feet) would be upgraded to match the urban section of Cedar Ridge Drive to the west. This segment of roadway is actually the extension of Cloud Street. Project Cost: $613,000 To be financed from Special Assessments, contingent on district formation. Relocation of Fire Station #4. Relocate Fire Station # 4 to Crawford and Markley Road in order to provide service as the community develops eastward. This project has been identified as appropriate for aesthetic enhancements under the City's Community Art and Design policy, which provides for up to 5% of the project cost to be allocated for that purpose. Cost estimate is $1,500,000. Requested for 2013. Downtown Drainage Improvements Drainage improvements to facilitate drainage at several downtown locations. Cost estimate for identified areas is perhaps $300,000, but need a better assessment of need. Downtown Gateways Install four gateways into the Downtown as identified in the Comprehensive Plan. Cost projection is on the order of $200,000 South Ninth Street, Riffel to Water Well Reconstruct South Ninth Street from a point just south of Riffel Drive to Waterwell Road, including reconstruction of the intersections and traffic control at Lowes Drive. Reconstruction of this segment is necessary due to the age and deteriorating condition of this major arterial providing service to a primary shopping and employment district. The project cost is estimated at $5,500,000 in 2009 dollars. 226 Magnolia Improvements from the Smoky Hill River Bridge to Markley Road. Reconstruct Magnolia to a 3 Lane urban section from the Smoky Hill River Bridge to Markley Road. Estimated cost of $1,500,000. Smoky Hill Bridge on East Magnolia. Reconstruct Bridge to match road segments. This project has been identified as appropriate for aesthetic enhancements under the City's Community Art and Design policy, which provides for up to 5% of the project cost to be allocated for that purpose. Estimated Cost: $1,500,000 Magnolia Road from Centennial to 1-135 Interchange This road improvement complements other infrastructure improvements in the area, and contemplates the improvement of this stretch of roadway to a three lane urban section. This project has been identified as appropriate for aesthetic enhancements under the City's Community Art and Design policy, which provides for up to 5% of the project cost to be allocated for that purpose. Estimated cost is approximately $3,000,000, and would be payable largely from General Obligation Bonds. Water Well Road from Centennial Road to Ohio Street. This project would improve Water Well Road to a three lane urban segment all along the Southern boundary of our Community, providing service to several critical Commercial and Industrial locations, as well as to potential future residential areas. The estimated cost is $4,000,000 Greeley Avenue Bridge Replacement of the Greeley Avenue over the old Smoky Hill River Channel. This project is estimated at a cost of $500,000 from General Obligation Bonds over a 10 year period. The estimated annual payment will be $62,000. This project has been identified as appropriate for aesthetic enhancements under the City's Community Art and Design policy, which provides for up to 5% of the project cost to be allocated for that purpose. The Community Art and Design Budget for this project has been set at $15,000. Note: Pending review of traffic patterns. Outcome could range from replacement to elimination of the structure. Improvements to East Cloud Street from Ohio to the Levee Reconstruction of this segment to an urban section, with curb, gutter, underground drainage, and turning lanes onto Ohio Street. Estimated Cost: $2,000,000 to be financed with Special Assessment bonds South Wellfield Improvements The Raw Water Supply Study identified a number of improvements to the South Wellfield and plant that will be necessary to insure a high quality reliable water supply through 2060. This project will incorporate a number of improvements to existing facilities, as well as new facilities that may be required. The "survey' cost estimate for the improvements is $21,650,000 in 2009 dollars. Funding source would be Water Revenue Bonds Prescott Drainage: Potential drainage improvements to East Prescott Avenue from Santa Fe to the Rail Road tracks. Cost estimate is $350,000. Downtown Parking, Trash Corrals This project would provide ancillary improvements -3 new and 11 expanded trash corrals. 227 This project has been identified as appropriate for aesthetic enhancements under the City's Community Art and Design policy, which provides for up to 5% of the project cost to be allocated for that purpose. Project Cost is estimated at $290,000. Unknown Funding Source. Salt Storage Building Construct a salt storage building to protect road treatment material from inclement weather, and to protect the environment from potential contamination from runoff from the storage location. 228 Debt Service Projections For Current and Future Projects 2012 2013 2014 2015 Summary Uses of Funds: Schedule J 2016 2017 2018 Total Existing Debt 5.95 5.96 5.95 5.95 5.95 5.95 5.95 At -Large $ 4,747,698 $ 4,744,062 $ 4,488,904 $ 5,120,973 $ 5,110,605 $ 5,089,272 $ 5,124,266 Property Owner Share $ 1,734,681 $ 1,725,441 $ 1,742,722 $ 1,578,388 $ 1,417,713 $ 1,262,580 $ 1,224,840 Enterprise Share $ 1,589,711 $ 1,611,625 $ 1,404,507 $ 961,403 $ 901,368 $ 887,162 $ 887,396 Total All Existing Issues $ 8,072,091 $ 8,081,128 $ 7,520,563 $ 6,576,096 $ 6,206,499 $ 5,825,759 $ 5,730,823 Total CIP At -Large $ $ $ 115,570 $ 1,084,667 $ 1,223,187 $ 1,413,255 $ 1,505,678 Property Owner Share $ $ - $ - $ - $ - $ - $ Enterprise Share $ $ - $ - $ - $ - $ - $ Total Future Projects $ $ - $ 115,570 $ 1,084,667 $ 1,223,187 $ 1,413,255 $ 1,505,678 Total, all At -Large $ 4,747,698 $ 4,744,062 $ 4,604,474 $ 6,205,640 $ 6,333,792 $ 6,502,527 $ 6,629,944 Property Owner Share $ 1,734,681 $ 1,725,441 $ 1,742,722 $ 1,578,388 $ 1,417,713 $ 1,262,580 $ 1,224,840 Enterprise Share $ 1,589,711 $ 1,611,625 $ 1,404,507 $ 961,403 $ 901,368 $ 887,162 $ 887,396 Total Issue/Project $ 8,072,091 $ 8,081,128 $ 7,636,133 $ 7,660,763 $ 7,429,686 $ 7,239,014 $ 7,236,501 Annual Change in At -Large Obligation $ (237,303) $ (3,636) $ (139,588) $ 1,601,165 $ 128,152 $ 168,735 $ 127,417 Sources of Funding Motor Vehicle Tax $ 300,000 $ 309,000 $ 318,270 $ 327,818 $ 337,653 $ 347,782 $ 358,216 Enterprise Funds $ 1,224,711 $ 1,311,625 $ 1,404,507 $ 961,403 $ 901,368 $ 887,162 $ 887,396 Special assessments $ 1,647,947 $ 1,604,660 $ 1,620,732 $ 1,467,901 $ 1,318,473 $ 1,174,199 $ 1,139,101 Prepaid Assessments (Escrow) $ 25,000 $ 25,000 $ 25,000 $ 25,000 $ 25,000 $ 25,000 $ 25,000 Delinquent Assessments Collected $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 50,000 Property Owner Share (CIP) $ - $ - $ - $ - $ - $ - $ - Transient Guest Tax $ 205,419 $ 209,527 $ 213,718 $ 217,992 $ 222,352 $ 226,799 $ 231,335 Delinquent Taxes $ 65,000 $ 58,016 $ 58,187 $ 59,252 $ 61,029 $ 63,470 $ 66,009 Miscellaneous Income $ 400,000 $ 100,000 $ 75,000 $ 75,000 $ 75,000 $ 75,000 $ 75,000 Transfer from Solid Waste $ - $ - $ - Transfer from Special Recreation $ 30,000 $ 30,000 $ 30,000 $ 30,000 $ 30,000 Sales Tax for Aquatic Center $ 1,350,000 $ 1,350,000 $ 1,350,000 $ 1,350,000 $ 1,350,000 $ 1,350,000 $ 1,350,000 Tax Stabilization Transfer" $ 250,000 $ 300,000 $ 200,000 $ 550,000 $ 550,000 $ 400,000 $ 250,000 Investment Income $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000 Subtotal, Non -Property Taxes $ 5,558,077 $ 5,357,828 $ 5,355,414 $ 5,124,365 $ 4,930,875 $ 4,609,413 $ 4,442,056 Property Taxes Required $ 2,514,013 $ 2,723,300 $ 2,280,719 $ 2,536,398 $ 2,498,811 $ 2,629,601 $ 2,794,445 Total Required: $ 8,072,091 $ 8,081,128 $ 7,636,133 $ 7,660,763 $ 7,429,686 $ 7,239,014 $ 7,236,501 "Stabilization Transfer 2015 - 2019 is for BiCentennial Project Produced $ 2,320,628 $ 2,327,498 $ 2,370,064 $ 2,441,166 $ 2,538,813 $ 2,640,366 $ 2,745,980 Projected Valuation 402,354,576 402,597,689 410,649,643 422,969,132 439,887,897 457,483,413 475,782,750 Required Levy rate 5.95 5.96 5.95 5.95 5.95 5.95 5.95 Current Year surplus (Deficit) $ (193,385) $ (395,802) $ 89,345 $ (95,231) $ 40,002 $ 10,765 $ (48,465) December 31 Fund balance (est.) $ 597,557 $ 201,755 $ 291,100 $ 195,869 $ 235,871 $ 246,635 $ 198,171 229 City of Salina, Kansas 2012 - 2017 CIP 1/3/2013 (A (A (A (A (A (A (A (A N U C N O O IT O O O 0 O 0 0 0 0 h O O 00 O CO Cl) 00 C c N O O O ' 000 M (O (00 M O N 03 C Q M O O M O 0 0 0 64 (A (A (A (A 69 O O O O LO O M N Cl) .O C E E .(6 E N N N OS (np Q Q c E L NM O N O O M h B O O r- O r- >m ��z2in O �°— 0aacM)0 O r r U') M M N N rq M N N (A 64 (A (A (A (A (A En (A (A 64 (A (A (A (A hcM7 LOLOO LO O O N O O M O Cl) O O q r O -i O q7 O O O O 0 IT 0 M O O O O 000 (A (A 64 (A (A (A O O O O O O O h LO LO h O I- C) O O 00 O O N Cl) Lr)O Cl) MIli M� O q O Co N M O LO N M r r EA (A 64 EA EA (A N O LO L L O O h (A (A (A (A (fi (A (A (A L Cl) LO� IT O � LO N N N N N N O O O O O O O lf) 0 O (» O O O O O O ' 0 0 O O LO O O O N O O O O O O O O 1-7 I- O C) M M M O M O Cl) O .q M r r r O Cl) Cl) (A O m O O r r m 00 0 000 N r M 0 h O I- Ld M L6 N O N (A (A (A (A (A (A (A fA (A QA fA O O O O O O H O 00 O O O ' O Cl) O 00 O O O 0000 (p OO Cl) M OM Cl) CIJ00 c ON r r EA EA EA EA (A (A Efi EA EA C O O O O O O O 0 0 0 O O O O 0 0 0 0 O O h O O (0 66 O Ld O 66 O O O O L6 to 00 O Cl0 O� Cl) M a- O Q y -coC) N r r C D_ �U 6PI, 6PI, 6PI, ��03�646c� 64646464 64 E CIO OOO 0 0 Co 000000 O 0 (n O O O 0 0 O O O Co Co Co Co 0 0 0 Co Co O O O 0 0 0 0 0 0 0 0 0 0 0' 0 O O O U) 0 0 O O h O O O O L6 O U0 0 0 M h M O 0 0 0 0 0 0 M r N O r N M O LO 2T O N r r U d C U) 64 EA (A (A (A (A (A (A (A EA (A EA (A (A 64 (A O O O O O O O O O O O O O O O O O O O O O O O O Co Co Co Co Co O Co O O Co O ' O O O 0 O L6 O O O Ld O L6 L6 M O 00 h O N 00 O LO N M r h M r Cl) Cl) Cl) Cl) M N r r (A (A (A (A (A (A (A (A (A (A (A (A (A (A (A (A (A (A (A (A (A N U N CD N O O IT O O O O O O O O O O h O O 00 O CO (n (n M ON C c N O O t (00 M (O (00 M O N 03 C Q M N q7 (M M M (A (A 64 (A (A (A (A 69 CD cli Cl) CN LO CD LO C 0 C C N> M C C C N f- N O .N .O C E E .(6 E N N N OS (np Q Q c E L O O Cl) (0000 O O O B O O r- O r- >m ��z2in CD¢¢2)0wii�mm �°— 0aacM)0 O N Cl) U') M M N M rq M N N (A 64 (A (A (A (A (A En O LO hcM7 LOLOO LO O O N O O M O Cl) O O q r O -i O q7 M 14 M r (A 64 (A (A 64 (A (A (A O O LO h LO LO h O I- C) O O Cl) IT r M N 0 N O M M MIli M� O q LO Cl) Co N M O LO N M 64 EA EA EA (A 64 EA EA (A O LO L L O O h N O h O L Cl) LO� IT O � LO N N N N N N (» (» ds ea (» (» (» (» O 000 (NO O LO O LO O h IT O N O N P-: N Ld h —76 1-7 O L O Cl) O M N r r N N .q q- (A (A (A (A (A (A (A O m O O m 00 0 000 O r M 0 h O I- Ld M L6 N O N ON M M O M N (A (A (A (A (A (A (A (A N U M d O N E N 0- U U N c (n (n M M OO Co �. d D_ U) N C C c N O O t U (D U N E 0) N O C -6 J N N E O N 03 C Q M J C M c M O y fT 03 '0 1 _N 0) d N N CO U W !n N <n 7 Q1 (n U` N p_ d O N� O (� e 7 Z) o o 0 0 3 o �n `� o (n .9 E Q (0 E E E O O m M M� C)> c N �'' Y •- m � J E N C O c E E 0) N C 0 C C N> M C C C N f- N O .N .O C E E .(6 E N N N OS (np Q Q c E L J 07 O �L � d' C .c C 03 .0 O d Q (n d N N 'O N U d� U U U C O O O 0) O "_ Y 03 7 m C U N U 6 (6 U U W 03 d U 0 W, 03 '7 V U 0 (l.. C O L CU C r U 0 O C j j N E O O N C _ M (n O p 0 cnn O >m ��z2in CD¢¢2)0wii�mm �°— 0aacM)0 O Cl) N City of Salina 2013 Sub-CIP 1/3/2013 BUILDINGS & FACILITIES Sales Tax Fire Pump Test Pit $50,000 Sales Tax Parks Resurface and Restripe Bill Burke Parking Lot $70,000 Golf Course Upgrade Restroom on back 9 $30,000 Sales Tax IBuilding Maintenance I upportin base for the boiler in Memorial H $30,000 1 BUDGET:$ 180,000 TOTAL Sales Tax $180,000 Utilities WWTP Repair Asphalt Driveway $17,000 WWC Install Doors on loafing shed $13,000 WWC Contrete Driveway and Sidewalk Section replacement at $25,000 Pump Stations B, 12, 16, C, A, 8,11,24,29 BUDGET:$ 60,000 TOTAL Utilities $55,000 TOTAL BUDGET: $ ESTIMATED COST TOTAL: YTD/BID COST TOTAL: REMAINING BUDGET: REMAINING FUNDS: $ 290,000 $255,000 $0 $35,000 290,000 City of Salina, Kansas 2013 Capital Budget 231 1/3/2013 City of Salina 2013 Sub-CIP PARK IMPROVEMENTS 1/3/2013 Fund Dept/Div. -oj. # Description Estimated Cost $130,000 YTD/BID COST TOTAL: $0 REMAINING BUDGET: $0 Special Parks PR-Rec. Payment on Bill Burke Soccer fields $30,000 Special Parks PR -Parks Replace Concrete Floor and Tables in Kenwood Shelter $16,000 Special Parks PR -Parks Park Amenities, tables, benches and grills in various parks $10,000 Special Parks PR -Parks Third Year of Park Sign Replacement Program $8,000 Special Parks PR -Parks Harmony Park Playground Equipment for Oakdale Park $10,000 Special Parks PR -Parks Athletic Field Turf Conversion $7,500 Special Parks PR -Golf Fleet Maintenance --Cart Batteries $11,500 Special Parks PR -Golf Annual Improvements to cart paths $7,000 Special Parks PR -Buildings Replace Concrete Entrances and Sidewalk at Carver Center $15,000 Special Parks PR-Rec. Ball Field Improvements at ECRA and Bill Burke $5,000 Special Parks PR-Rec. Improvements at Lakewood Discovery Center $10,000 Deferred Items (Pending project savings or budget amendment): Construct 1.4 mile trail connecting levee trail to South Ohio Trail at Schilling Road $18,000 Communication transition for irrigation and well operation $4,200 BUDGET:$ 130,000 TOTAL SPECIAL PARKS: $130,000 TOTAL CITY BUDGET: $130,000 PRIVATE DONATIONS: ESTIMATED COST TOTAL: $130,000 YTD/BID COST TOTAL: $0 REMAINING BUDGET: $0 REMAINING FUNDS: $130,000 232 City of Salina 2013 Sub-CIP 1/3/2013 STREET, TRAFFIC, and RAMPS Fund Gas Tax Dept/Div. Ramps Proj. # Description ADA Ramp Construction Estimated Cost $50,000 Gas Tax Street Arterial Sidewalk Construction $50,000 Gas Tax Traffic Traffic Cameras At three intersections $30,000 Gas Tax Traffic Battery Backups and LED Lights $50,000 Gas Tax Street Bridge Inspection and Maintenance $25,000 Gas Tax Street Annual Pavement Marking $20,000 Gas Tax Street Crack Sealing $350,000 Gas Tax Street Concrete Rehabilitation $594,000 Gas Tax Street Centennial Road Design $148,000 Gas Tax Railroad Crossing (1) $50,000 BUDGET: $ •. TOTALeee Sales Tax Mill and Inlay $700,000 Sales Tax Microsurfacing $500,000 Sales Tax Railroad Crossing (1) $50,000 Sales Tax Downtown Alley Drainage Improvements $90,000 Sales Tax BUDGET: $ 1,380,000 Annual City Parking Lot Improvements TOTAL$1,380,000 $40,000 TOTAL BUDGET: $ ESTIMATED COST TOTAL: $ YTD/BID COST TOTAL: $ REMAINING BUDGET: $ REMAINING FUNDS: $ 233 2,747,396 2,747,000 2,747,396 2,747,396 City of Salina 2013 Sub-CIP 1/3/2013 VEHICLES & EQUIPMENT General Street Pull Behind Asphalt Tack Machine $15,000 General Street Salt Spreader, New, Unit 121 $20,000 General Street Snow Plow, Unit 121 $11,000 General Fire Stryker Power Cots 3 $49,800 General Fire Stryker Patient Loading System $28,000 General Fire Mini -Van replacing unit 411 Cit Pool $28,000 General Fire Replace two (2) Zoll 12 -lead cardiac monitors $54,000 General Fire Type I Ambulance $195,000 General Parks 72" out front mower withcab and snow removal attachment Unit 1126 $40,000 General Parks Convert Unit 1342 (1995) to Electric Power $16,000 General Parks 72" out front mower withcab and snow removal attachment Unit 1384 $40,000 General BUDGET: Parks $500,000 Electric Utility Vehicle TOTAL GENERAL: $15,000 $511,800 Central Garage Sales Tax Central Garage 000 Street Convert 2002 vehicle to Electric (unit 250) TOTAL Road Maintenance Paver $16,000 $16,000 $50,000 Sales Tax Street Replacement Backhoe (unit 134?) $70,000 Sales Tax Street Traffic Lift Truck 45' $70,000 Sales Tax Golf Reel type fairway mower $47,000 Sales Tax Flood Control 25' Pull Behind Mower Deck $20,000 Sales Tax Building Services Compact Pickup or Hatchback $20,000 Street Salt Spreader (replace unit 116-2 $13,000 Sales Tax BUDGET: Fire $300,000 Cardiac Science AED's a)__ TOTAL SALES TAX: $10,000 $300,000 Golf Course Sanitation Sanitation Sanitation lGolf iii Sanitation Sanitation 960 I Golf Cart Batteries (34) 1 TOTAL Golf: Replace Unit 565 (25 Yard capacity) Other Equipment (Containers?) TOTAL SANITATION:960 $18,000 $18,000 $156,000 $54,960 Solid Waste Solid Waste Solid Waste Solid Waste BUDGET: Landfill Landfill Landfill Landfill $63,000 3/4 Ton 4X4 Pickup with Snow Plow Alternative Daily Cover Tarps (2) Riding mower, mid -mount zero -turn Off Road 6X4 ATV TOTAL SOLID WASTE: $35,000 $8,500 $10,000 $9,500 $63,000 Utilities Water Distribution Replace Fire Hydrants $56,000 Utilities Water Distribution Provide stock of new meter s $30,000 Utilities Water Distribution Rehabilitate Well # 12 $70,000 Utilities Water Treatment VFP Drives for 2 High Service Pumps $60,000 Utilities Water Treatment Rehabilitate One River Station Pum $30,000 Utilities Water Treatment Replace Two 2 Ammonia Feeders $23,000 Utilities Water Treatment Replace six turbidimeters $17,000 Utilities Wastewater Treatment Add screw pump station to SCADA $25,000 Utilities Wastewater Treatment Inline Solids Meter $25,000 Utilities Wastewater Treatment Replace Effluent Flow Meter $10,500 Utilities Wastewater Collection Replace two 2 Pumps at Station 7 $28,000 $400,000 TOTAL00 TOTAL BUDGET: $1,489,960 ESTIMATED COST TOTAL: $1,476,260 YTD Total Bids $0 YTDBudget Savings $0 YTD/BID COST: $0 REMAINING BUDGET: $1,489,960 234