2464 Street Improvements1
1
i
1
ORDINANCE NO.. 2464 _
r
(_Publ.i:she_d_in_The=Sa.1-i-na—E'veming—J.Q-= l=lLar_chT1-/ -1922.}
An Ordinance.speeifying and selecting the paving material to
be used and letting a contract for the paving, excavating,
curbing and.guttering of certain streets in the City of
Salina, Kansas.
BE IT ORDAINED by the Board of Commissioners of the .City of
Salina, Kansas:.
Section 1. That it is hereby determined that Ohio Avenue
in the City of Salina, Kansas, from the'north line of Iron Avenue
to the south line of Ash Street in said City, shall be paved with
one course vitrified vertical fiber side wire out brick paving
blocks not less than three (3) inches deep, with Texaco Asphalt
Filler or filler equally as good, laid on a foundation of Five (5)
inches in depth of Portland Cement Concrete base with one (1)
inch Sand Cushion, such pavement within the limits above defined
to be Thirty-three (33) feet in width from gutter to gutter.
Sedtion 2. That it is hereby determined that Ohio Avenue
in the City of Salina, Kansas, from'the north line of Iron Avenue
to the south line of Ash Street in said City, shall be curbed
and guttered with one-piece combination cement curb and gutter.
Said combined curb and gutter shall be comprised of a curb six
(6) inches thick at the top and six and one-half (62) inches thick
at the throat, with combined gutter twenty-four (24) inches wide,
six (6) inches thick at the throat and seven (7) inches thick next
to the pavement.
Section 3. All excavating, filling and rolling necessary
for the proper construction of such improvements shall be done
and all of such improvements shall be. made and done in strict
conformity to and in compliance with the plans and specifications
heretofore made by the City Engineer of Salina, Kansas and now on
file with the City Clerk of said City, which said plans and spe-
cifications are hereby incorporated in and made a part hereof in
all respects as fully and completely as'though written out at
length herein;'which plans and specifications are hereby adopted
as and -for the plans and specifications of such work and improve-
ments.
Section 4. That a contract -is hereby awarded to G. -M.
Smith and Mat,Graham, Jr., co-partners doing business under the
firm name and style of the Smith -Graham Construction Company, for
the paving, curbing, guttering, excavating and filling of the abom
mentioned streets in the limits aforeadid with the materials here-
inbefore specified, for the paving actually laid and put in place
and for the labor actually performed and the materials actually
furnished at the following prices; for excavating and grading,
seventy-two cents (72�).per cubic yard; for Portland Cement
Concrete combined curb and gutter, eighty-two cents (82�) per
lineal foot; for paving actually laid and put in place Three
and 23/100 Dollars ($3.23) per square .yard. All of said work
shall be paid for according to the measurement made by the
City.Engineer of the City of Salina, It is hereby determined
and found that the prices to be paid.for the improvements as
aforesaid is less than the estimated prices of each and all of
said improvements as now on file with the City.Clerk of the
City of Salina, Kansas.
Section 5. Such contract is awarded upon the express
condition that such work and improvements shall.be done in strict
.accordance with and in compliance with the plans -and specifica-
tions of the City Engineer therefor, which plans and specifica-
tions are hereby made a part of this ordinance and.of the contract
-awarded, and upon further conditions.among others that the per-
sons to whom said contract is awarded shall furnish to the City
,of -Salina a surety company bond in the approximate sum of the
cost.of such improvements guaranteeing the prompt, proper and
workmanlike construction of all the same together with a surety
company bond guaranteeing such pavement against all defects in
material and workmanship for a period of five -(5.) years from
the date of its.completion and -acceptance by said City; and
said contract is awarded upon a further condition that said
persons shall furnish to the City of Salina a good and'suffi-
cient surety company bond.guaranteeing said curb and gutter
against all defeets.in material and workmanship for a period of
two (2) years from the date of its completion and acceptance
of such work by said city, together with a good and sufficient
surety company bond running to the State of Kansas in an amount
approximately equal to the contract price of said improvements
and conditioned that said persons shall pay all indebtedness
for labor and material furnished in making the improvements pro-
vided for herein.
Section 6. The Board of Commissioners of the City of
Salina, are hereby authorized to make and enter into on behalf
of said City all written.agreements-necessary in order to se-
cure the construction of the improvements herein provided for.
1
1
1
1
1
1
1
0
i
1
Section 7. This ordinance shall take effect and be in
.full force from and after its publication once in the official
City paper.
Passed and approved, March 6th, 1922.
_ F_ _.. S . Dyar ,
(SEAL) Mayor
Attest:
Chan. E. Banker
City ClerR.
STATE OF KANSAS )
) SS.
COUNTY OF SALINE )
I. Chas. E. Banker, -City Clerk of the city of Salina,
Kansas, do hereby certify that the above and foregoing is a true
and correct copy of Ordinance Number -2464 passed by the Board of
Commissioners and approved by the Mayor of the.City of Salina,
Kansas, ' Ma.rch 6th, 1922; and a record of the vote on its final
adoption is found on Page �1 %7 of Journal No. 9. Said Ordinance
was published in The Salina Evening Journal March //,,!�Z 1922„
City Clerk.
(Published in the Salina Evening Journal March //;-t 1022 )
ORDINANCE NO.
An Ordinance specifying and selecting the paving material to
be used and letting a contract for the paving, excavating,
curbing and guttering of certain streets in the City
of Salina, Kansas..
:BE IT ORDAINED by the Board of Commissioners of the City of
Salina, Kansas:
Section 1. That it is hereby determined that Ohio Avenue
in the City of Salina, Kansas, from the north line of Iron Avenue
to the south line of Ash Street in said City, shall be paved with
one course vitrified vertical fiber side vire out brick paving
blacks not less than three (3) inches deep, with Texaco Asphalt
Filler or filler equally as good, laid on a foundation five (5)
inches in depth of Portland Cement Concrete base with one (1)
inch. Sand Cushion, such pavement within the limits above defined
to be Thirty -Three (33) feet in width from gutter
to gutter.
Section 2. That it is hereby determined that Ohio Avenue
in the City of Salina, Kansas, from the north line of Iron Avenue
to the south line of Ash Street in said City, shall be curbed,
and guttered with one-piece combination cement curb and gutter.
Said combined curb and gutter shall be comprised of a curb sig
(6) inches thick at the top and six and rine-half (621) inches thick
at the throat, with combined gutter twenty-four (24) inches Fide,
six (6) inches thick at the throat and seven (7) inches thick: next
to the pavement.
Section 3. All excavating, filling and rolling necessary
for the proper construction of such improvements shall be done
and all of such improvements shell be made and done in strict
conformity to and in compliance with the plans and specifications
heretofore made by the City Engineer of Salina, Kansas and noir on
file with the City Clerk of said City, which said plans and spe-
cificationsrare hereby incorporated in and made a part hereof
K
in all respects as fully and completely as though written oat
at length herein; which plans and specifications are hereby
adopted as and for the plans and specifications of such work
and improvements*
Section 4. That a contract is hereby awarded to G. M.
Smith and Mat.Graham Jr., co-partners doing business under the
firm name and style of the Smith -Graham Construction. Company,
for the paving, curbing, guttering, excavating and fill-
ing of the above mentioned streets in the limits aforesaid with
the materials hereinbefore specified, for the paving actually'
laid and put in place and for the labor actually performed and the
materials actually furnished at the following prices; for exca.
vating and grading, seventy-two cent. (72�) per cubic yard; for
Portland Cement Concrete combined curb and gutter, eighty-two
cents (8W per lineal foot; for paving actually laid and put
in place Three and 23/100 Dollars ($3.23) per square yard. All
of said work shall be paid for according to the measurement made
by the City Engineer of the City of Salina. It is hereby deter-
mined and found that the prices to be paid for the improvements
as aforesaid is less than the estimated prices of each and all of
said improvements as now on file with the City Clerk of the City
of Salina, Kansas.
Section 5. Such contract is awarded upon the express condi-
tion that such work and improvements shall be done in strict ac-
cordance with and in compliance with the plans and specifications
of the City Engineer therefor, which plans and specifications are-.
hereby made a part of this ordinance and of the con -tract awarded,
and upon further conditions among others that the persons to whom
said contract. is awarded shall furnish to the City of Salina a
compsny
surety,bond in the approximate sum of the cost of such improvements
prompt
guaranteeing the/ -proper and workmanlike construction of all the
same together with a surety company bond guaranteeing such pave-
ment against all defects in material and workmanship for a period.
a V
of five (5) years from the date of its completion and acceptance
by said City; and said contract is marded upon a further condition
that said persons shall furnish the City of Salina a good and suf-
ficeint surety company band guaranteeing said curb and gutter against
all defects in material and workmanship for a period of two (2 )
years from the date of its completion and acceptance of such work
by said City, together with a good and sufficient suretydompany bond
running to the Mate of Kansas in an amount approximately equal
to the contract price of said improvements and conditioned that
said persons shall pay all indebtedness .for labor and material
furnished in making the improvements provided for herein.,
Section 6. The Board of Commissioners of the City of
Salina, are hereby authorized to make and enter into on behalf of
said. City all written agreements necessary in order to secure the
construction of the improvements herein provided for,
Section 7, This (rdinance shall take effect and be in full
force from and after its pullication once in the official City
paper.
Introduced for first reading
Passed gnd approved March kith! 1922
Attest: `" yor
City Clerk.