Change Order No. 1 for the 1995 Subdivision Improvement Project No.
95-938.
BACKGROUND
The attached Change Order No. 1 includes water and sanitary sewer
system relocations at the proposed Magnolia/I-135 Interchange
project. These utility relocations are one of the final items to
complete for the interchange project prior to the December il, 1995
deadline established by the Kansas Department of Transportation.
It has been determined by staff that this negotiated change order
on an existing utility contract is the most expediant and cost-
effective method of completing this essential project.
The total cost of Change Order No. 1 is $13,645. The contractor,
Stevens Contractors, Inc. has committed to completing the work in
20 calendar days. The source of funds for this change order is the
Magnolia/I-135 Interchange project account, the budget for which
included contingency amounts for this type of utility relOcation.
RECOMMENDATION
It is recommended that the City Commission approve Change Order No.
1 on the 1995 Subdivision Improvements Project No. 95-938 in the
amount of $13,645.
CHANGE ORDER
LOCATION: MAGNOLIA/I-135 INTERCHANGE PROJECT NO. 95-938
PROJECT: 1995 SUBDIVISION IMPROVE~RNT$ CHANGE ORDER NO. ONE (1)
CONTRACTOR: STEVENS CONTRACTORS,INC,, P. 0. BOX 6197, SALINA. KS 674Q2
THIS AGREEMENT, made and entered into this 6th day of November ,
1995 , by and between the CITY OF SALINA, KANSAS, Owner, and the above
named Contractor, modifies the existing contract dated October 9. 1995,
under the above subject, project and project number in the following
particulars to wit:
1. The specifications and drawings for certain street improvements in
the City of Salina, Kansas, dated September - 1~9~ , are hereby amended
in the following particulars only; all other terms and conditions remain
unchanged.
I~m No. Description
21 Add relocation of existing "6" Water Pipeline" to revised
right-of-way line for Magnolia/I-135 Interchange, 850 linear
feet.
23 Add "Water Pipeline Fittings" for the relocation of 6" Water
Pipeline at Magnolia/I-135 Interchange, 0.43 Ton.
40 Add installation of "Special Type I Manhole" for the
relocation of .existing sewer system at Magnolia/I-135
Interchange, one (1) each.
64 Increase "Water" needed for pipeline installation, one (1)
lump sum.
65 Increase "Construction Staking" for pipeline installation,
one (1) lump sum.
67 Add "Relocation of existing Fire Hydrant, one (1) each.
68 Add "Removal of existing Fire Hydrant, one (1) each.
69 Add "8" Sewer Plug", one (1) each.
CHANGE ORDER
PAGE 2
2. The undersigned proposes to furnish all tools, appliances,
equipment, materials, and labor required to complete the construction in
a thorough, workmanlike, and satisfactory manner in accordance with the
drawings, specifications, and contract documents, for the following
prices:
ITEM UNIT
NO ~ DESCRIPTION 0UANTITY UNIT PRICE TOTAL
21 6" Water Pipeline 850 L.F.$ 11.00 $ 9.350.00
23 Water Pipeline Fittings 0.43 Ton 4.000.00 1. 720,
40 Type I Manhole, Special i EA. 1,500.00 1.500,O0
64 Water 1 L.S. 50.00 50
65 Construction Staking I L.S. 425.00 42§. 00
67 Relocate Existing Fire Hydrant i EA. 300.00 300.00
68 Remove Existing Fire Hydrant I EA. 200.00 200.00
69 8" Sewer Plug i EA. ] 00.00 , ] 00.00
CHANGE ORDER TOTAL: $ ]3~645.00
3. Additional time for completion by reason of this change ,20 days.
4. All other terms and conditions of the contract to remain unchanged.
OWNER, FIRST PARTY CONTRACTOR, SECOND PARTY
THE CITY OF SALINA, KANSAS STEVENS CONTRACTORS, INC.
BY: BY: ~ MAYOR
~'/~
(Office or position 'of signer)
Attest:
CITY CLERK