CO 1 Museum Millwork
..
CHANGE ORDER
LOCATION:
211 West Iron. Salina KS 67401
PROJECT NO. 04-1506
PROJECT: Smoky Hill Museum Gallery Millwork
CHANGE ORDER NO. One (1)
CONTRACTOR: Highland Millshop. Inc. . 2116 S.E. Pennsylvania Ave.. Topeka Kansas 66605
THIS AGREEMENT, made and entered into this
28th
day of October
2005
,by
and between the CITY OF SALINA, KANSAS, Owner, and the above named Contractor, modifies the existing
contract dated April 4th. 2005
, under the above subject, project and project number in the
following particulars to wit:
1. The specifications and drawings for certain remodeling improvements in the City of Salina, Kansas, dated
March. 2005 , are hereby amended in the following particulars only; all other terms and conditions
remain unchanged.
ITEM NO.
DESCRIPTION
2
Add for extra glass and doors on gift shop display case.
2. The undersigned proposes to furnish all tools, appliances, equipment, materials, and labor required to complete
the construction in a thorough, workmanlike, and satisfactory manner in accordance with the drawings,
specifications, and contract documents, for the following prices.
-1-
....
CHANGE ORDER
PAGE 2
ITEM NO.
DESCRIPTION
QUANTITY
UNIT
PRICE
1
Extra glass and doors for gift shop display case
EA
$312.00
1
Total:
3. The contract time for completion by reason of this change
0
days.
4. All other terms and conditions ofthe contract to remain unchanged.
OWNER, FIRST PARTY
CONTRACTOR, SECOND P ARTY
THE CITY OF SALINA, KANSAS
HIGHLAND MILLSHOP INC.
BY, .~~
CITY MANAGER
B~~
ÝL /;aa- s
(Office 06r position of signer)
Attest~ C fJ /1'" J -
CITY CLERK ~
-2-
TOTAL
$312.00
$312.00