8.10b Awd Golf Course Apron CITY OF SALINA
REQUEST FOR COMMISSION ACTION DATE :rIME
].2/22/97 4:OO P.M.
AGENDA SECTION: ORIGINATING DEPARTMENT: APPROVED FOR
NO, 8 AGENDA:
Engineering & General Servia:es
ITEM
NO. 10 b
BY: Shawn O'Leary~ BY: '~
ITEM
Award of contract for the Municipal Golf Course Clubhouse Apron Construction, Project No. 97-
1085.
BACKGROUND
Pursuant to the previous item involving Change Order No. 1 for the Municipal Golf Course Cart
Path Project, this item includes the award of contract to a local contractor for the reconstruction of
the clubhouse apron. Bids were received for this project on Wednesday, December 17, 1997 as
follow:
BIDDER BID AMOUNT SCHEDULE
Faubion Concrete, Salina $24,244.80 Jan. 1- Feb. 14, 1998
Davis Construction, Bennington $24,486.00 Jan. 1 - Apr. 30, 1998
General Services Const., Salina $29,414.40 Dec. 29,1997- Mar. 29, 1998
Wilbur Construction, Salina $30,183.60 Jan. 1 - Mar. 31, 1998
Lancaster Construction, Salina $30,528.00 Jan. 1 - Apr. 30, 1998
Pavers, Inc., Salina $31,566.00 Jan. 5 - Mar. 5, 1998
Engineer's Estimate $30,360.00
All bids are valid and qualified. The anticipated total underrun in the Municipal Golf Course Cart
Path Project is $34,535.00, therefore the low bid above will yield a net difference of ($10,290.20)
in that project budget. At the same time, the golf course project will be finished in a more timely
manner to allow less disruption during the playing season.
RECOMMENDATION
It is recommended that the City Commission award the contract for the Municipal Golf Course
Apron Construction, Project No. 97-1085, to Faubion Concrete in the amount of $24,244.80.