CHANGE ORDER
LOCATION:. 925 E. North Street PROJECT NO. 04-1463
PROJECT: Curb and Gutter and Concrete Pavement Improvements CHANGE ORDER NO. One (1)
CONTRACTOR: Wilbur Construction Co 1707 Upper Mill Terrace Salina Kansas 67401
THIS AGREEMENT, made and entered into 10TH day of February 2005 , by
and between the CITY OF SALINA, KANSAS, Owner, and the above named Contractor, modifies the existing
contract dated April 26, 2004 , under the above subject, project and project number in the
following particulars to wit:
1. The specifications and drawings for certain street improvements in the City of Salina, Kansas, dated
March - 2004 , are hereby amended in the following particulars only; all other terms and conditions remain
unchanged.
ITEM NO. DESCRIPTION
2. Add "Remove and Replace Reinforced Pavement" to correct major deficiencies in a section of
pavement at 925 E. North Street, 275 square yards.
13. Add "Traffic Control' due to the volume of traffic and the necessity of detouring of traffic for
approximately 14 days; sign rental; placement and removal of signs; and monitoring of signs
during construction, 1 lump sum.
2. The undersigned proposes to furnish all tools, appliances, equipment, materials, and labor required to complete
the construction in a thorough, workmanlike, and satisfactory manner in accordance with the drawings,
specifications, and contract documents, for the following prices:
-1-
" CHANGE ORDER
PAGE 2
ITEM
NO. DESCRIPTION
2 Remove & Replace Reinforced Pavement
13 Traffic Control
CHANGE ORDER TOTAL:
QUANTITY UNIT
275 S.Y.
1 L. S.
UNIT
PRICE TOTAL
$ 31.50 $ 8,662.50
$ 1,080.00 $ 1,080.00
3. The contract time for completion by reason of this change -6" / f days.
4. All other terms and conditions of the contract to remain unchanged.
OWNER, FIRST PARTY
THE CITY OF SALINA, KANSAS
BY:
JRN�U&rY ANAGER
Attest:
CONTRACTOR, SECOND PARTY
WILBUR CONSTRUCTION CO.
BY:
"o*4'
(Office or position of signer)
-2-
$ 9,742.50