6.9 Change Order for Bill Burke Turf Improvements for FencingCITY OF SALINA REQUEST FOR CITY COMMISSION ACTION DATE TIME 01/23/2023 4:00 P.M. AGENDA SECTION ORIGINATING DEPARTMENT: FISCAL APPROVAL: NO: 6 BY: Parks and Recreation Department ITEM FINAL APPROVAL: NO: 9 Page 1 BY: Jeff Hammond BY: Xk—:5", ITEM: Consider Authorizing the City Manager to Approve a Change Order for Project #22031, Bill Burke Turf Improvements to Nemaha Sports Construction for Certain Fencing Improvements in the amount of $52,791.00. BACKGROUND: The Bill Burke Memorial Park planned improvements will convert eight (8) grass infields to synthetic turf with underdrainage, fencing and dugout improvements, add an additional bathroom to the North end of the facility and replace the existing central bathroom facility to allow for the remodel of the existing concession facility. Additionally, improvements are being planned for Berkley Family Recreational Area to address drainage issues of the existing fields due to being adjacent to the former airport runway. On July 11, 2022, the City Commission approved for the City Manager to execute a contract for engineering design services with Schwab -Eaton, P.E. for $239,000.00 for engineering services for the Bill Burke Memorial Park and Berkley Family Recreational Area Infield Turf and Park Improvements Project. At the request of Salina Baseball Enterprises, Wilbur Field and Matson Field at Berkley Family Recreational Area were included as an add alternate. The City authorized the design and specifications of those infields for that purpose. On October 17, 2022, the City Commission awarded the bid and authorized the City Manager to execute a construction contract for project number #22031 for synthetic turf improvements for 8 infields at Bill Burke Memorial Park to Nemaha Sports Construction in the amount of $1,726,000.00. The notice to proceed was provided to Nemaha Sports Construction on November 7, 2022 and construction started shortly afterward. To date, storm drainage to take water off the fields to the river for fields 4-6 has been completed and Nemaha is currently working on storm drainage for fields 1-3. Completed work on fields 2, 4, 5 and 6 includes excavation to the proper depth, grading, most of the concrete curb and turf anchoring strip, installation of a non -porous liner, HDPE sub -drainage pipe and a base of aggregate rock material. The concrete curb surrounding the infield serves as an edge for the containment of the sub -drainage and additionally serves as an attachment point for the synthetic turf. The concrete curb will not be visible once the turf is installed. The City's original intent for part of the Phase 2 of Bill Burke improvements is to replace the existing 4' galvanized posts and fencing with 6' black coated posts and fencing with one (1) rolling gate opening along the sidelines of each field. The City believed the fencing and gates would be a standalone project for Phase 2 of Bill Burke construction. The proposed one (1) rolling gate per field would serve as the main entrance onto the field for turf groomers, mowers, tractors and utility vehicles. The proposed design of a 16' rolling gate would straddle the new synthetic turf and natural grass in order for equipment to access the corresponding CITY OF SALINA REQUEST FOR CITY COMMISSION ACTION DATE TIME 01/23/2023 4:00 P.M. AGENDA SECTION ORIGINATING DEPARTMENT: FISCAL APPROVAL: NO: BY: ITEM Parks and Recreation Department FINAL APPROVAL: NO: Page 2 BY: Jeff Hammond BY: surface. The desired footers for the 6' fence posts and rolling gate would be in the same location as the concrete curb and anchor strip for the turf. It has become apparent that it would be more effective for the turf concrete curb and anchor strip to accommodate the posts and concrete footer for the fencing and gate. The proposed change order transfers a portion of the fencing work that was anticipated in Phase 2 of the Bill Burke project to the current scope of work. The areas in question are adjacent to the dugouts and extending to the edge of the new synthetic turf for all 8 fields. The change order is not for all the fencing replacement anticipated in Phase 2. The proposed scope of work for Phase 2 fencing includes new side line fences and posts from the dugout to outfield, new rolling gates for each field, new fencing around frame work of dugout, backstop board replacement, backstop wire mesh replacement. All wire mesh will be black vinyl coated fencing. The change order includes the posts and the associated concrete, excavation and dirt work that would support the proposed fence mesh and gate (1 per field) from the dugout to the edge of the synthetic turf on each field on both sides. Lastly, Nemaha has requested in the change order for an extension of the contract by 10 days to complete the work outlined below. Staff have reviewed the scope of work and pricing of the change order and believe it to be competitively priced. FISCAL NOTE: During the 2022 Budget discussions, the City Commission indicated their desire to fund $1,500,000 of the City's share with cash and fund the remaining $2,500,000 with bonds to be paid for with Transient Guest Tax revenue. The project funding balance is as follows: Remove Existing 4' Posts, Footings &Backfill $3,878.00 Nemaha 88 New 6'x 2.7/8" Fence Posts &Footings $24,000.00 Sub Contract Excavation &Backfill for Curb $2,292.00 Nemaha Material &Labor for Concrete Curb $10,600.00 Sub Contract Additional Backfill &Grading to curb base $3,503.00 Nemaha Added Sod for areas impacted $1,456.00 Nemaha Construction Layout $1,000.00 Nemaha Collars for 5 drain basins $1,263.00 Nemaha Overhead (Approximately 10%) $4,799.00 Nemaha Total $52,791.00 AGENDA SECTION NO: ITEM NO: Page 3 CITY OF SALINA REQUEST FOR CITY COMMISSION ACTION DATE TIME 01/23/2023 4:00 P.M. ORIGINATING DEPARTMENT: Parks and Recreation Department BY: Jeff Hammond Beginning Project Budget $4,000,000.00 Schwab Eaton Design & Engineering ($238,000.00) CXT Bathroom Units ($342,310.00) Synthetic Turf Improvements ($1,726,000.00) Geotechnical Services — Kaw Valley ($14,990.50) Proposed Change Order ($52,791.00) Remaining Project Balance $1,625,908.50 COMMISSION ACTION OR RECOMMENDED ACTION: Staff has identified the following options for the City Commission's consideration: FISCAL APPROVAL: 9W 1.) Authorize the City Manager to Approve a Change Order for Project #22031, Bill Burke Turf Improvements to Nemaha Sports Construction for Certain Fencing Improvements in the amount of $52,791.00. 2.) Authorize the City Manager to Approve a Change Order for Project #22031, Bill Burke Turf Improvements to Nemaha Sports Construction for Certain Fencing Improvements in the amount of $52,791.00 with amendments as the City Commission deems appropriate. 3.) Postpone consideration of the proposed Change Order to a specified date and time and provide staff direction regarding additional information or amendments the City Commission would like to request for their further consideration. 4.) Take no action (in effect, disapproving the proposed Change Order). Staff recommends Option #1 Attachments: Nemaha Request for Change Order including drawings CC: Schwab Eaton, P.E. Ira I Nemaha .�;r• r,��Nsrm1 Nemaha Landscape Const., Inc. 541 S 1st ST Lincoln, NE 68508 Nemaha Sports Construction 541 S 1 st St. Lincoln, NE 68508 (402) 434-5488 - Office (402) 434-5487 - Fax Request for Change RFC Number: 3 Date: 01/13/2023 Regarding: Fence PR Pricing To: Job Site: Schwab Eaton Salina- Bill Burke Park 1125 Garden Way 300 W. Ash St. PO Box 736 Manhattan, KS 66502 Salina, KS 67402-0736 Requested By: Phone: JE -mail: Kyle King (402) 434-5471 kyle.king@nemaha.net Recipients: Phone: E-mail: Judson Gladin Requested Change: Change to Contract See attached for breakout of time & cost impacts. $ 52791.00 Add 10 working days to the contract which includes the fence demo and curb prep time, fence material lead time, time to schedule and install the fence posts, time to reschedule the concrete sub, time to complete the curb install after the completed post install, and time to complete the backfill/re-grading of these areas before turf. Direction is needed by 1/24/2023, or For additional background on the added time: more added time will be necessary, - 1 day fence removals which equates to 1 added day for - 4 days fence scope each day passing beyond 1/24, until - 3 days concrete scope a direction is received. - 2 days to piece work together after fence/concret/*11ship e (agg base, grading, nailer, etc.) Speaking with Sprinturf the morning of 1/19/2023, the turf 1/30/2023 and be on site 2/1/2023. If a direction is not received to allow for a start of turf on 2/1/2023, additional time impacts will be incurred and sent to the owner for approval. Please respond by: 01/17/2023 K e ing Nemaha Landscape Construction RFC Total $ 52791.00 Judson Gladin Schwab Eaton Pricing and time impacts Added fence post removals, haul off of posts/footings materials and backfill of holes to allow for new work = $3,878.00 o L = $2,953 o E = $550 Additional breakout is o S = $375 provided at the end of New fencing subcontractor per PR = $24,000.00 this document. o See attached text from Bill Hurtig. ■ Note the text says $2,900, ut after I asked him to see if he can expedite material, he said he could only expedite if we use 2-7/8" posts for everything — the corner and line posts, and that is an added $100/field. • Please confirm 2-7/8" is acceptable for ALL post sizes in this PR. Added concrete subcontractor costs = $10,600.00 K— o See attached quote and explanation from thkconcrete subcontractor. ■ In addition to the added LF of curb an he wider curb, the fence sub indicated that this is largely the added cost to piece hese together since these should already have been completed with the rem . der of the field curb that is already installed. He will have to come back fo these areas specifically, as the other 4 fields won't be ready where he could tac at that time. Let me know if this doesn't make sense. I attached what correspon ence that I had w/him on this. Additional breakout is Excavation and backfill for extra curb = $2,292.00 provided at the end of o L = $1,772 this document. o E = $520 Added time for piecing the edges together (additional backfill, additional grading of the base, etc.) = $3,503.00 o L = $2,953 o E = $550 Added sod for additional area impacted = $1,456.00 o L = $696 o M = $440 o E = $320 Added layout = $1,000.00 Collars for five (5) nyloplast drain basins as indicated = $1,263.00 o L = $738 o M = $250 o E = $275 Total with 10% OH = $52,791.00 o Approximately $6,599.00/field Add 10 working days to the contract which includes the fence demo and curb prep time, fence material lead time, time to schedule and install the fence posts, time to reschedule the concrete sub, time to complete the curb install after the completed post install, and time to complete the backfill/re-grading of these areas before turf. Direction is needed by 1/24/2023, or For additional background on the added time: more added time will be necessary, -1 day fence removals which equates to 1 added day for - 4 days fence scope each day passing beyond 1/24, until - 3 days concrete scope a direction is received. - 2 days to piece work together after fence/concrete 's done (agg base, grading, nailer, etc.) Speaking with Sprinturf the morning of 1/19/2023, the tur ill ship 1/30/2023 and be on site 2/1/2023. If a direction is not received to allow for a start of turf on 1/2023, additional time impacts will be incurred and sent to the owner for approval. a u sesue>l 'eulleS v� � a� U0103 T s�uawanoadwI �nl �!4@ 4U (S 8 u 00 °o gemg3S eaay !euo!4eaa�ad �(!!we,j /�al�!aa9 A E p4� '�!@Mne !!!9 pQd lid € " �401 o& s; � 1go oc a� Am URI, C� Ali \- � 3 Out o�� s ut - s JAY 2 C c e jai ��s \ o _ k$'?�� h8seWilt � s a � � i \ W p a Q \ /oLN \ \\:\\\ \ \Xo.t \ \ \:. \ \•\'\\ \\.\\\•\ \ IN,IN \N,g\\\\ \.\ \\\ \X \ \\\, \\\. '\ \ .\' \\\\\\ \\\\\\ \ - \\\\\\\\x\.\\\\. \\\ \\\\ `\`\`\ \\`\: \ \:`\`\ \' `\ \ .I\�` \ 3 p N T N� H sssa��asasg�eRRR��$,$s $$�s s_ sse�assssecscssssssss os�aaagFR;sxaa��q����q�� o& s; � 1go oc a� Am URI, C� Ali \- � 3 Out o�� s ut - s JAY 2 C c e jai ��s \ o _ k$'?�� h8seWilt � s a � � i \ W p a Q \ /oLN \ \\:\\\ \ \Xo.t \ \ \:. \ \•\'\\ \\.\\\•\ \ IN,IN \N,g\\\\ \.\ \\\ \X \ \\\, \\\. '\ \ .\' \\\\\\ \\\\\\ \ - \\\\\\\\x\.\\\\. \\\ \\\\ `\`\`\ \\`\: \ \:`\`\ \' `\ \ .I\�` \ 3 p N T N� UOIB3 T sesue)i 'eu!les 4a sIuauaanoadwI 6uiauaj gemgos V2d alan9 II!9 s t U o �s o 8 5{ w �W/Hv .fir n Z Vol, 351 ,PWS /M \ W LL fid' Pvi °� Q W U. e /°tom Md, 15 w 1 1 1� V ah I � I gi \\ ucc ucc � Y+n W� � w �i �„pW � s5 T s5 J W U. U0183 s'eulles gUMgos sIuauiaAo-ioaduaI 6u!ouaj m o -!j79-1 >la�d a�an9 II!9 6u cB S i� U0183 sesue>l leups S4U@W9Ao-idwj buiouaj q �Jed mane 11!9' Lrl �sr 6u E qyamqos o NO, d d2 002 110 11111. MomfkN : ,am% w Ramirez lump sum price. Breakout also attached in this document. y Al� r s. —F- 4.� • Q Additional breakout from Ramirez �O ry t ,^ m U N Ln iii r� LJ L c U c1, fV ti 00 � Z Kyle Icing Additional breakout from Bill Hurtig From: Kyle King Sent: Wednesday, January 18, 2023 2:02 PM To: Judson Gladin; Hammond, Jeff; Reinert, Troy Cc: Kyle King Subject: Fencing breakout from Bill Hurtig Team - Just talked to Bill. Verbal breakout below. Feel free to call him if you would like. - L = $500.00 - M = $1,980.00 and includes posts and concrete materials (he said $125/each for the posts and $55/each for the concrete) - E = $420.00 - Total = $2,900.00/field o Added $100.00/field to make it $3,000.00/field and this is to increase the post size (because the larger post size is available whereas the size on the plans has a longer lead time). This $100.00/field adder to increase the post sizes will decrease the post lead time from 2-3 weeks to 2-3 days as this larger post is available, whereas the other is not. Let me know of any other questions. Appreciate the time talking through things today. Good luck! Thanks, Kyle King, CFB, CTB NEMAHA SPORTS C❑NSTRuCTI❑N 541 S. 1sT STREET LINCOLN, NE 68508 OFFICE: (402) 434-5488 I FAX: (4112) 434-5487 CELL: (402) 430-1 552 I KYLE. KINGPNEMAHA.NET CF'B _ _RCER7T1F1ERQTR-ACKfiUl1DERan CERTIFi ELD BUILDER GA 1