Change Order 1
CHANGE ORDER
LOCATION:
Crawford Street: 60 feet west of Centennial Rd. to 9th Street
PROJECT NO.
04-1429
PROJECT: 2004 -2005 Spring and Fall Street Marking
CHANGE ORDER NO. One (1)
CONTRACTOR: Twin Traffic Marking Corporation. 4100 VanDe Popouliere. Kansas City. Mo. 64150
THIS AGREEMENT, made and entered into this
5th
day of October
2004
, by
and between the CITY OF SALINA, KANSAS, Owner, and the above named Contractor, modifies the existing
contract dated
April 26. 2004
, under the above subject, project and project number in the
following particulars to wit:
1. The specifications and drawings for certain utility improvements in the City of Salina, Kansas, dated
March. 2004 , are hereby amended in the following particulars only; all other terms and conditions remain
unchanged.
The items listed below are for the 2004 Fall Pavement Markin!! only.
ITEM NO.
DESCRIPTION
Crawford Street: 60 feet west of Centennial Rd. to 9th Street
1. Add 5,520 lineal feet of Double Continuous Yellow
4. Add 1,030 lineal feet of Single Solid White
5. Add 2,540 lineal feet of Single Broken White
2. The undersigned proposes to furnish all tools, appliances, equipment, materials, and labor required to complete
the construction in a thorough, workmanlike, and satisfactory manner in accordance with the drawings,
specifications, and contract documents, for the following prices:
1
CHANGE ORDER
PAGE 2
ITEM
NO. DESCRIPTION
QUANTITY
UNIT
UNIT
PRICE
TOTAL
PRICE
1. Double Continuous Yellow 5,520 LF, @$ 0.18 $ 993.60
4. Single Solid White 1,030 LF. @$ 0.09 $ 92.70
5. Single Broken White 2,540 LF, @$ 0.09 $ 228.60
CHANGE ORDER TOTAL $ 1.314.90
3. The contract time for completion by reason ofthis change
0
days.
4. All other terms and conditions of the contract to remain unchanged.
OWNER, FIRST PARTY
CONTRACTOR, SECOND PARTY
THE CITY OF SALINA, KANSAS
TWIN TRAFFIC MARKING, CORPORATION
By:Ø~~?
CITY MANAG R
BY:
(Office or position of signer)
AttetÆ di~ t;;b
CITY CLERK -- r
2