Loading...
6.4 CO1 S Marymount Road CITY OF SALINA REQUEST FOR CITY COMMISSION ACTION DATE 12/17/01 TIME 4:00 P.M. AGENDA SECTION: NO. 6 ORIGINATING DEPARTMENT: APPROVED FOR AGENDA: Engineering & General Services ITEM NO. 4 BY: ITEM Change Order No. 1 for the South Marymount Road Improvements, Project No. 01-1274. BACKGROUND This change order on the South Marymount Road Improvement Project involves five additional items of work to complete the storm drainage portion of the project. The majority of these items are due to field plan changes to improve the effectiveness of the overall drainage system. The others were simply unforeseen circumstances that caused the overruns. The contract date for this project was August 28, 2001. The total amount of this change order is $14,151.72. The original contract amount with APAC-Kansas, Inc., Shears Division was $988,794.70. If approved, this change order will result in a 1.4 percent increase in the total contract amount or $1,002,946.42. The majority of the additional costs included in this change order will be paid by the City as opposed to an allocation of additional special assessments to the benefit district because the additional work relates to the storm drainage improvements. The project is on schedule. The majority of the storm drainage improvements in the corridor have been completed and placed into service. Currently, the major drainage structure at the south end of Marymount Road is under construction. Upon completion of that structure in January, 2002, the existing roadway will be reopened to through traffic until the Spring, 2002. The final phase of construction, involving the reconstruction of the street and the addition of a continuous sidewalk, will take place between March-July, 2002. RECOMMENDATION It is recommended that the City Commission approve Change Order No. 1 for the South Marymount Road Improvements, Project No. 01-1274, with APAC-Kansas, Inc., Shears Division in the amount of $14,151.72. CHANGE ORDER LOCATION: SOUTH MARYMOUNT ROAD PROJECT NO. 01 -1274 PROJECT: SOUTH MARYMOUNT ROAD IMPR. CHANGE ORDER NO.--.l CONTRACTOR: APAC-KANSAS. INC.. SHEARS DIVISION TillS AGREEMENT, made and entered into this 18 day of December 2001, by and between the CITY OF SALINA, KANSAS, Owner, and the above named Contractor, modifies the existing contract date August 28TH 2001 Under the above subject, project and project number in the following particulars to wit: 1. The specifications and drawings for certain Subdivisions Improvements in the City of Salina, Kansas, dated July 2001 , are hereby amended in the following particulars only; all other terms and conditions remain unchanged. ITEM DESCRIPTION 10 Add 18.4 S.Y. of6" Bituminous Pavement (Commercial Grade) to allow completion of access road between Fairdale Rd. and Eastview Dr. 22 Add 10 L.F. of Storm Sewer (30" RCP) to complete connection at Crawford St. 35 Add two (2) Special Cone. Type IV Area Inlets at Sta 31 + 32 Lt. and Rt. as per plan revision. 36 Add one (1) Manhole (ReinE Cone.) at Sta. 44 + 50 Lt. as per plan revision. 42 Add 124 C.Y. of Foundation Stabilization at Sta. 21 + 24.09 to improve sub-base conditions under new 6' x 12' RCB 2. The undersigned proposed to furnish all tools, appliances, equipment, materials, and labor required to complete the construction in a thorough, workmanlike, and satisfactory manner in accordance with the drawings, specifications, and contract documents, for the following prices. CHANGE ORDER PAGE 2 ITEM NO. DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL 10 6" Bituminous Pavement 18.4 S.Y. $13.30 $244.72 22 Storm Sewer (30" RCP) 10.0 L.F. $47.30 $473.00 35 Special Cone. Type IV Area Inlets 2.0 EA. $2,217.30 $4,434.60 36 Manhole (Reinforce Concrete) 1.0 EA. $1,695.80 $1,695.80 42 Foundation Stabilization 124.0 c.Y. $58.90 $7,303.60 CHANGE ORDER TOTAL: $ 14.151.72 3. Additional time for completion by reason ofthis change 0 days. 4. All other terms and conditions ofthe contract to remain unchanged. OWNER, FIRST PARTY CONTRACTOR SECOND PARTY THE CITY OF SALINA, KANSAS BY: BY: MAYOR/CITY MANAGER (Office or position of signer) Attest: