1.0 CIMCITY COMMISSION INFORMATION MEMORANDUM ADMINISTRATIVE BRIEF FROM MARTHA TASKER UTILITIES DEPARTMENT March 15, 2021 South Well Field and Water Treatment Plant Construction Update South Well Field and Water Treatment Plant (WTP) Project: 3.5 MGD Lime Softening WTP Rehabilitate four wells 7,000 L.F. of 10 - 20 inch raw water main • Burns & McDonnell/CAS Constructors, Topeka — Design -Build Team Project Cost: Funded by Kansas Public Water Supply Loan Fund • Construction Cost: $29,399,695 • Cost to Date: $27,868,316.70 (Through 0212812021) —95% Completed Construction/Plant Start Up: • Start Date: February 2019 • Confirmed process equipment meets the project requirements • Confirmed water quality meets all federal and state regulatory requirements • WTP in operation/Treated water to Water Distribution System: March 9, 2021 • Partial Substantial Completion: March 9, 2021 • Final Completion: July 2021 TRANSFER PUMP STATION CLEARWELL WASHWATER BASIN BEHIND CHEMICAL HIGH SERVICE BUILDING BUILDING PUMP STATION FILTER BUILDING T. February 2021: Panoramic view of site — South side looking north LIME SPLITTER BOX & SODA ASH SOFTENING SILOS BASINS Filter Building Exterior r44 - "%%"MOP Filter Building Interior Filter Building Pipe Gallery Chemical Building Exterior and CO2 Storage Chemical Building East Room Chemical Building West Room High Service Pump Station Exterior High Service Pump Station Pump Room Transfer Pump Station/One Million Gallon Clearwell Softening Basins & Splitter Box Water Well No. 105 Lime & Soda Ash Silos