1.0 CIMCITY COMMISSION INFORMATION MEMORANDUM
ADMINISTRATIVE BRIEF FROM MARTHA TASKER
UTILITIES DEPARTMENT
March 15, 2021
South Well Field and Water Treatment Plant Construction Update
South Well Field and Water Treatment Plant (WTP) Project:
3.5 MGD Lime Softening WTP
Rehabilitate four wells
7,000 L.F. of 10 - 20 inch raw water main
• Burns & McDonnell/CAS Constructors, Topeka — Design -Build Team
Project Cost: Funded by Kansas Public Water Supply Loan Fund
• Construction Cost: $29,399,695
• Cost to Date: $27,868,316.70 (Through 0212812021) —95% Completed
Construction/Plant Start Up:
• Start Date: February 2019
• Confirmed process equipment meets the project requirements
• Confirmed water quality meets all federal and state regulatory requirements
• WTP in operation/Treated water to Water Distribution System: March 9, 2021
• Partial Substantial Completion: March 9, 2021
• Final Completion: July 2021
TRANSFER
PUMP
STATION
CLEARWELL
WASHWATER
BASIN BEHIND CHEMICAL
HIGH SERVICE BUILDING BUILDING
PUMP STATION FILTER BUILDING
T.
February 2021: Panoramic view of site — South side looking north
LIME
SPLITTER BOX &
SODA ASH
SOFTENING SILOS
BASINS
Filter Building Exterior
r44 - "%%"MOP
Filter Building Interior
Filter Building Pipe Gallery Chemical Building Exterior and CO2 Storage
Chemical Building East Room
Chemical Building West Room
High Service Pump Station Exterior High Service Pump Station Pump Room
Transfer Pump Station/One Million Gallon Clearwell Softening Basins & Splitter Box
Water Well No. 105
Lime & Soda Ash Silos