6.4 Change Order No. 2 for the 2017 Water Main Replacement Project No. 2, Project No. 70016CITY OF SALINA REQUEST FOR CITY COMMISSION ACTION DATE TIME 02/22/2021 4:00 P.M. AGENDA SECTION ORIGINATING DEPARTMENT: FISC4APPVAL: NO: 6 BY: UTILITIES DEPARTMENT FINAAL: ITEM N0: 4 Page I BY: Martha Tasker M A f BY: ITEM: Approve Change Order No. 2 for the 2017 Water Main Replacement Project No. 2, Project No. 70016, Kansas Public Water Supply Loan Fund (KPWSLF) Project No. 2957. BACKGROUND: Refer to the Water Main Replacement Overview for background information. In August 2018, the City Commission authorized staff to execute KPWSLF Project No. 2957 in the amount of $4,250,000. Two projects were bid as follows: • Project 1: Construction by Smoky Hill, LLC with a bid amount of $2,097,103 • Project 2: Construction by Stevens Contractors, Inc. with a bid amount of $1,516,587 In November 2018, the City entered into an agreement with Stevens Contractors, Inc. for the amount of $1,516,587, which included the replacement of approximately 2.7 miles (4,710 linear feet (L.F.) of 12 -inch, 5 L.F. of 10 -inch, 4,614 L.F. of 8 -inch, and 4,700 L.F. of 6 -inch) of water main replacements. In July 2019, Change Order No. 1 was approved to add approximately 0.45 miles (1,300 L.F. of 8 -inch and 1,050 L.F. of 6 -inch) of water main replacements, which allowed the KPWSLF loan amount to be better utilized. The Contract Price was increased by $234,507, and the Contract Time was increased by 80 calendar days. The additional work was priced per the bid letting unit prices and was located in the vicinity of work being performed by the Contractor. The attached Change Order No. 2 adjusts the contract's quantities to reflect actual quantities installed, and additional work completed at Bond and Fifth Streets and Charlotte Avenue between Highland Avenue and Ninth Street Place by the Contractor. Change Order No. 2 also revises the Contract Time, including time for the increase in actual quantities installed and additional work at OCCK on Schilling Road. During construction, decisions and adjustments often have to be made in real-time to respond to conditions identified in the field. Much of Salina's water infrastructure was constructed between 1900 and 1960, and there are no record drawings available to determine field conditions. Due to differences between the plans and actual field conditions encountered, several field changes were necessary to construct the project, which included additional water pipeline footage, valves, and fire hydrants, removing and replacing 24 -inch meter pits in new locations, and moving tie- in locations to avoid below ground conflicts. Bond Street and Fifth Street Additional concrete and asphalt pavement, curb and gutter, sidewalk, and wheelchair ramps were ocation, which added 118.8 L.F. of 6- removed and replaced. This was the result of moving a tie-in l inch water pipeline that was under the street, sidewalk, and wheelchair ramps. The unit prices are from the Salina Public Works Fee Schedule, Resolution No 18-7593. The cost breakdown is as follows: 8 -inch Concrete Pavement: Replace Asphalt: Curb & Gutter: Sidewalk: Wheelchair Ramp Type I: 83.3 S.F. @ $8.251S.F. = 131.5 S.F. @ $9.50/S.F. = 19.0 L.F. @ $30.00/L. F. = 264.9 S.F. @ $6.15/S.F. = 2 ea. @ $675.00 = Total: $ 687.23 $1,249.25 $ 570.00 $1,629.14 $1,350-00 $5,485.62 CITY OF SALINA REQUEST FOR CITY COMMISSION ACTION DATE TIME 02/22/2021 4:00 P.M. AGENDA SECTION ORIGINATING DEPARTMENT: FISCAL APPROVAL: NO: BY: UTILITIES DEPARTMENT FINAL APPROVAL: ITEM NO: Page 2 BY: Martha Tasker BY: Charlotte Avenue between Highland Avenue and Ninth Street_ Place Additional concrete pavement and curb and gutter were removed and replaced. The location of the new 6 -inch line was re-routed out into the street to maintain a 10 -foot clearance between a sanitary sewer manhole and the new water pipeline, per the Kansas Department of Health and Environment design standards. The unit prices are from the Salina Public Works Fee Schedule, Resolution No 18- 7593. The cost breakdown is as follows: Pavement Sawing: 101 L.F. @ $4.101L. F. = $ 414.10 Remove Curb and Gutter: 20.7 L.F. @ $2.00/L.F. = $ 41.40 Remove Concrete Pavement: 113.5 S.F. @ $1.25 S.F. = $ 141.88 Replace Curb and Gutter: 20.7 L.F. @ $30.00 L.F. = $ 621.00 Replace 8 -inch Concrete Pavement: 113.5 S.F. @ $8.25/S. F. = 936.38 Total: $2,154.76 The main changes to the quantities are as follows: +$ 7,720 • Added 110.3 L.F. — 12 -inch Water Pipeline +$ 26,950 e Added 573.4 L.F. — 6 -inch Water Pipeline +$ 13,500 . Added 3 each — Fire Hydrants +$ 32,825 . Added 21 each — 6 -inch and 12 -inch Valves and Tapping Sleeves/Valves +$ 55,400 . Added 41 each — 1 -inch, 1.5 -inch, 2 -inch Long and Short Service Lines +$ 23,700 . Added 79 each — Remove Existing Water Meter Pit +$ 80,400 • Added 67 each — Install 24 -inch Water Meter Pit (New Location) +$ 15,000 . Added 5 each — Remove and Replace 36 -inch Water Meter Pit (New Location) +$ 5,485 . Added work at Bond Street and Fifth Street + 2,155 e Added work at Charlotte Avenue Between Highland Avenue and Ninth Street Place +$263,135 -$ 3,765 . Reduced 64.9 L.F. — 8 -inch Water Pipeline -$21,600 . Reduced 12 each — 1.5 -inch Short Service Lines (Two Service Lines Each) -$ 6,600 + Reduced 60 L.F. — Remove and Replace 6 -inch Sanitary Sewer Main -$55,100 . Reduced 58 each -- Remove and Replace 24 -inch Water Meter Pit (Same Location) -$10,800 e Reduced 4 each — Remove and Replace 36 -inch Water Meter Pit (Same Location) -$97,865 Net Difference = +$165,270 AGENDA SECTION NO: CITY OF SALINA REQUEST FOR CITY COMMISSION ACTION DATE TIME 02/22/2021 4:00 P.M. ORIGINATING DEPARTMENT: I FISCAL APPROVAL: UTILITIES DEPARTMENT ITEM NO: Page 3 BY: Martha Tasker The revised Contract Price is as follows: CHANGE IN CONTRACT PRICE BY: FINAL APPROVAL: BY: Contract Price: $1,516,587.00 Change Order No. 1: $ 234,507.00 Change Order No. 2: $ 152,321.980} Revised Total Contract Amount: $1,903,415.98 (1) $167,221.98 - $14,900 (149 days at $100 per day) for liquidated damages. Changes in Contract Time is as follows: Additional Time for work at OCCK 1710 West SchillingRoad The Contractor had mobilized to this area, staked out the location of the new water pipeline per the plans, saw cut and removed pavement, located existing utilities, and installed a portion of the new water pipeline. A main break occurred on the existing 6 -inch water pipeline under a loading dock on the north side of the building. The existing water pipeline that broke was installed in 2014. Staff determined that to avoid future costly breaks under the loading dock, it would be a most cost-effective and long-term solution to reroute the water pipeline around the loading dock. Additional time was required to lay out the new location of the water pipeline, exposing utilities and mobilizing in and out of the work area. A total of 14 additional calendar days is proposed for this delay. In addition, a total of 95 calendar days is proposed for the increase in actual quantities installed and additional work completed by the Contractor, resulting in the Contract Time being increased by 109 calendar days. CHANGE IN CONTRACT TIME Project Completion November 19, 2020 December 19, 2020 ')June 23, 2020 to November 19, 2020=149 Calendar Days x $100.00 = $14,900.00 Liquidated Damages. Substantial Completion is the date on which construction is sufficiently complete in accordance with the Contract Documents so that the City can use the Project for its intended purpose. Final Completion is the date on which all construction is complete in accordance with the Contract Documents and is the commencement date for the two-year warranty period. Refer to the attached Change Order No. 2 for detailed information on revisions to Contract Price and Contract Time. Substantial Completion Final Completion Notice to Proceed January 16, 2019 January 16, 2019 +335 Calendar Days +365 Calendar Days Construction Completion December 17, 2019 January 16, 2020 +80 Calendar Das +80 Calendar Days Change Order No. 1 March 6, 2020 April 5, 2020 +109 Calendar Days +109 Calendar Days Change Order No. 2 June 23, 2020 July 22, 2020 +149 Calendar Days0) +149 Calendar rlavg0) Project Completion November 19, 2020 December 19, 2020 ')June 23, 2020 to November 19, 2020=149 Calendar Days x $100.00 = $14,900.00 Liquidated Damages. Substantial Completion is the date on which construction is sufficiently complete in accordance with the Contract Documents so that the City can use the Project for its intended purpose. Final Completion is the date on which all construction is complete in accordance with the Contract Documents and is the commencement date for the two-year warranty period. Refer to the attached Change Order No. 2 for detailed information on revisions to Contract Price and Contract Time. CITY OF SALINA REQUEST FOR CITY COMMISSION ACTION DATE TIME 02/22/2021 4:00 P.M. AGENDA SECTION ORIGINATING DEPARTMENT: FISCAL APPROVAL: NO: BY: ITEM UTILITIES DEPARTMENT FINAL APPROVAL: NO: Page 4 BY: Martha Tasker BY: FISCAL NOTE: The 2017 Water Main Replacement Projects No. 1 and No. 2 are funded through the KPWSLF with a loan amount of $4,250,000. Current Project Costs are as follows: Project 1 Project 2 Contract Price $2,097,103 $1,516,587 Change Order No. 1 $ 28,900 $ 234,507 Change Order No. 2 $ 0 $ 152,322 Total Contract Amount $2,126,0030) $1,903,416 = $4,029,419 0) Estimated pending adjustments to contract quantities to reflect actual quantities installed. The 2021-2025 Water and Wastewater Rate Study includes an annual payment of $267,058 at an interest rate of 2.33%. The first payment was due in 2020 and will continue through 2040. COMMISSION ACTION OR RECOMMENDED ACTION: Staff has identified the following options for the City Commission's consideration: 1.) Approve Change Order No. 2 for the 2017 Water Main Replacement Project No. 2, Project No. 70016, KPWSLF Project No. 2957 to Stevens Contractors, Inc. of Salina, Kansas in the amount of $152,321.98 (Revised Total Contract Amount, $1,903,415.98), and revise the Contract Time for Substantial Completion from March 6, 2020, to November 19, 2020. 2.) Postpone approval of Change Order No. 2 for the 2017 Water Main Replacement Project No. 2 to a specified date and time and provide staff direction regarding additional information or amendments the City Commission would like to request for their further consideration. 3.) Vote to deny Change Order No. 2 for the 2017 Water Main Replacement Project No. 2. Staff recommends Option 1. Attachments: Change Order No. 2 Water Main Replacement Overview c:ijity"r UTILITIES DEPARTMENT TELEPHONE: 785-309-5725 300 West Ash - P.O. Box 736ti FAX: 785-3095713 Sauna, Kansas 67402-0736 WEBSITE - www-selina-ks.gov CHANGE ORDER PROJECT: 2017 Water Main Replacement. Project No. 2 PROJECT #: 70016 LOCATION' Various Locations CHANGE ORDER No.: 2 (two) CONTRACTOR' Stevens Contractors, Inc. DATE OF CONTRACT: December 16 2018 1. DESCRIPTION OF CHANGE This Change Order adjusts the contract quantities to reflect actual quantities installed, additional work completed at Bond and Fifth Streets and Charlotte Avenue Place by Contractor, and revises Contract Time, including additional time for work at OCCK on Schilling Road, between Highland Avenue and Ninth Street the Additional Item No. DESCRIPTION OF CHANGE Change Unit Price Total Days 1 Quantity Adjustment- Water Pipeline, 12 -inch Change construction quantity of 4,710 LF by: 110.3 LF $ 70.00 $ 7,721.00 3.81) Revised Total Construction Quantity: 4.820.3 LF 2 Quantity Adjustment - Water Pipeline, 10 -inch 5 LF by: 13.5 LF $ 100.00 $ 1,350.00 0.50 Change construction quantity of Revised Total Construction Quantity: 18.5 LF 3 Quantity Adjustment -Water Pipeline, 8 -inch Change construction quantity of 5,916 LF by: (64.9) LF $ 58.00 $ (3,764.20) (1.10) Revised Total Construction Quantity: 5,851.1 LF 4 Quantity Adjustment -Water Pipeline, 6 -inch Change construction quantity of 5,753 LF by: 573.4 LF $ 47.00 $ 26,949.80 10.00 Revised Total Construction Quantity: 6,326.4 LF 5 Quantity Adjustment - Fire Hydrant & Valve Assembly Change construction quantity of 28 EA by: 3 EA $ 4,500.00 $ 13,500.00 3.10 Revised Total Construction Quantity: 31 EA 7 Quantity Adjustment - Tapping Sleeve, Valve S Valve Box (12" x 12") Change construction quantity of 2 EA by: i EA $ 6.400.00 $ 6,400.00 1.75 Revised Total Construction Quantity: 3 EA 10 Quantity Adjustment - Tapping Sleeve, Valve & Valve Box (6" x 6") Change construction quantity of 2 FA by: 1 EA S 3.859.00 $ 3,850.00 1.00 Revised Total Construction Quantity: 3 EA 11 Quantity Adjustment - Resilient Gate Valve, 12 -inch Change construction quantity of 7 EA by: 1 EA $ 2,700.00 $ 2,700.00 0.50 Revised Total Construction Quantity: 8 EA 12 Quantity Adjustment - Resilient Gate Valve, 8 -Inch 13 EA by: 3 EA S 1,375.0 S 4.125.00 1.25 Change construction quantity of Revised Total Construction Quantity: 16 EA 13 Quantity Adjustment - Resilient Gate Valve, 6•Inch 11 EA by: 15 EA 5 1.450.00 $ 15,750.00 4.20 Change construction quantity of Revised Total Construction Quantity: 26 EA 14 Quantity Adjustment - Long Service, 2 -Inch Change construction quantity of 12 EA by: 5 EA $ 1,900.00 $ 9,500.00 5.00 Revised Total Construction Quantity: 17 EA 15 Quantity Adjustment - Short Service, 2 -Inch 2 EA by: 1 EA $ 1,700.00 $ 1,700.00 0.70 Change construction quantity of Revised Total Construction QuantJty: 3 EA 16 Quantity Adjustment - Long Service, 1.5 -inch 3 EA by: 4 EA $ 2000.00 $ 8,000,00 2.80 Change construction quantity of Revised Total Constrcclion Quantity: 7 EA 17 Quantity Adjustment - Short Service, 1.5 -Inch Change construction quantity of 13 EA by: (12) EA $ 1,800.00 $ (21,600,00) (5.00) Revised Total Construction Quantity: 1 EA 18 Quantity Adjustment - Long Service, 1 -Inch 72 EA by: 13 EA $ 1,400-00 $ 18,200,00 6.40 Change construction quaintly of Revised Total Construction Quantity: 85 EA 19 Quantity Adjustment - Short Service, 1 -Inch 69 EA by: 18 EA $ 1,000.00 $ 18,000.09 6.30 Change construction quantity Of Revised Total Construction Quantity', 67 FA 22 Quantity Adjustment - Remove & Replace 6 -inch Sanitary Sewer Main Change construction quantity of 60 LF by: (60) LF $ 110.00 $ (6,600.00) (2.80) Revised Total Construction Quantity. - LF 23 Quantity Adjustment - Existing Line Valves Abandoned Change construction quantity of 52 EA by: 3 EA S 200.00 $ 600.00 IN Revised Total Construction Quantity: 55 EA 29 Quantity Adjustment - Remove Existing Water Meter Pit Change construction quantity of 9 EA by: 79 EA S 30000 $ 23,700.00 22.00 Revised Total Construction Quantity: 88 EA 30 Quantity Adjustment- Remove & Replace 244n Water Meter Pit (Same Location) Change construction quantify of 154 EA by: (58) EA $ 950.00 $ (55,100.00) (32.50) Revised Total Construction Quantity: 96 EA 31 Quantity Adjustment - Install 24 -In Water Meter Pit (New Location) Change construction quantity of 10 EA. by: 67 0 $ 1,200.00 $ 80,400.06 56.30 Revised Total Construction Quantity: 77 EA All requirements of the Contract Documents shall apply to the performance of the work. OWNER. FIRST PARTY CONTRACTOR, SECOND PARTY CITY OF SALINA KANSAS STEVENS CONTRACTORS, INC Additional Item No. DESCRIPTION OF CHANGE Change Unit Price Total Days Added CO #1 Quantity Adjustment - Remove 8 Replace 36 -in Water Meter Pit (Same Location) Date 32 Change construction quantity of 5 EA by: (4) EA $ 2,700.00 $ (14.800.00) (4.29) Revised Total Constructon Quantity: 1 EA Added CO ill Quantity Adjustment - Remove 8 Replace 36 -in Water Meter Pit (New Location) 33 Change construction quantity of 3 EA by: 5 EA $ 3,000.00 $ 15,000.00 7.00 Revised Total Construction Quantity 8 EA Added CO #2 Additional Work at Bond Street and Fifth Street 34 Change construction quantity of - LS by: 100 LS $ 5.485.62 $ 5,485.62 3.50 Revised Total Construction Quantity: 1.00 LS Added CO #2 Additional Work at Charlotte Avenue between Highland Avenue and Ninth Street Place 35 Change construction quantity of - LS by. 9.09 LS $ 2,154.76 $ 2.154.76 3.50 Revised Total Construction Quantity: 1.09 LS Added CO #2 Additional Time for work at OCCK on Schilling Road - $ $ - 14 36 Number of Days Added: 109 Nei Increase: $ 167,221.98 Liquidated Damages= $ (14,900.00) O1 Total: $ 152,321.98 Original Contract Price: $ 1,516,587.00 Change Order No. 1: $ 234,507.00 Change Order No. 2. $ 152,321.98 Revised Total Contract Price: $ 1,903,415.98 t'r$167,221.98 • $14,900 (149 days at $100 per day) for Liquidated Damages 2. CHANGE IN CONTRACT TIME SUBSTAINTlAL COMPLETION FINAL COMPLETION Notice to Proceed January 16 .2019 January 16, 2019 Calendar Days: +335 +365 Origin[ Contract Completion Date: December 17. 2019 January 16, 2020 Calendar Days: +80 +80 Change Order No. 1 March 6. 2020 April 5, 2020 Calendar Days: +109 +109 Change Order No. 2: June 23, 2020 July 22, 2020 Calendar Days: +149" +1491 Completion Date: November 19, 2020 December 19, 2020 "June 23, 2020 to November 19, 2020=149 Calendar Days x $100.00 = $14,900.110 Liquidated Damages. All requirements of the Contract Documents shall apply to the performance of the work. OWNER. FIRST PARTY CONTRACTOR, SECOND PARTY CITY OF SALINA KANSAS STEVENS CONTRACTORS, INC 300 W. Ash Street P.O. Box 1276 Salina, Kansas 67402 Salina, KS 67462 12 Martha A. Tasker, Director of Ctilites Quentin Robl, Owner Melissa Rose Hodges, Mayor Date Date Attest: city Clerk Water Main Replacement Overview February 22, 2021 The 2007 Water Distribution Water Model identified existing cast iron water mains that required replacement. In 2010, the City Commission approved $20 Million to be debt- financed for Water Main Replacements. It was anticipated that $4 Million would be completed each year and would be divided into projects to allow local/multiple contractors to complete the projects and potentially reduce the project construction time. Beyond the initial $20 Million of water main replacements, the intention was to continue the annual water main replacements utilizing cash on hand, which is scheduled to begin in 2021 at $2.0 Million per year. The water distribution system consists of 340 miles of water mains ranging in size from 2 -inch to 30 -inch diameter pipes. The original distribution system was constructed in the early 1900s, and the majority of that construction took place in the early 1900s through the 1960s. The water main material was cast iron, which was cast in sand molds. These old sand cast iron water mains were not uniform in size and were not cement -lined, which resulted in a rough interior of the water mains, which provides a surface for iron bacteria to attach to. The water system consists of 195 miles of cast iron water mains (60% of total water mains), of which 133 miles are 6 -inches or smaller in diameter. Old, unlined cast iron water mains often develop tuberculation that gradually constricts flow and causes water flow discoloration due to corrosion products. The results of tuberculation are low fire flows and the presence of iron bacteria, which causes taste and odor complaints. Fire hydrant flushing and other cleaning methods can be performed to reduce tuberculation; however, re -growth of the incrustations is very rapid and flushing and cleaning are not permanent solutions. Tuberculation is problematic in the water mains that are 6 -inch and smaller, over 50 years in age, and where velocities in the water mains are low. Water main replacements are necessary when preventative maintenance activities are no longer effective. The status of the water main replacement projects are as follows: Project/Construction Date Cost Miles Phase 1 (2010 — 2011) $ 776,239 2.0 Phase II 2011 -- 2012 $ 993,760 2.6 Phase III 2013 — 2015 $ 1,423,680 2.0 Phase IV 2013 — 2015 $ 1,222,047 3.5 Phase V (2013 — 2015) $ 1,375,349 3.5 Phase VI (2014 — 2016) $ 1,941,432 4.5 Phase VII (2014 — 2016) $ 2,340,146 4.1 2016 (2016 — 2018) $ 2,104,025 2.9 2017 Project No. 1 2019 — 2020 $ 2,126,003 3.7 2017 Project No. 2 2019 — 2020 $ 1,903,416 3.2 2019 Project No. 1 2021 — 2022 $ 1,871,700 2.6 2019 Project No. 2 2021 — 2022 1,998,39A 3.0 Total $20,076,121 37.6 A total of $20,076,121 has been financed over a ten year period, which totals 37.6 miles of water main replacements. This is an average of 3.76 miles per year at a cost of $533,939 per mile, or an annual cost of $2,007,612.