Notice To proceed WWTP Phase 1ANOTICE TO PROCEED
Date: 12/15/2020
Project: Phase 1A of the Wastewater Treatment Plant Improvement Project
Owner: City of Salina, Kansas
Contract: Phase lA of the Wastewater Treatment Plant
Improvement Project
Contractor: Overland Contracting Inc.
Contractor's Address: 11401 Lamar
Overland Park, Kansas 66211
Owner's Contract No.: 20028
KWPCRF Project No.: C20 2049 01
You are notified that the Agreement Times under the above Agreement will commence
performance of the services set forth in this Agreement within five (5) days of this Notice to
Proceed dated December 15, 2020 unless the parties mutually agree otherwise in writing. Design -
Builder shall complete such services for Phase 1A no later than April 30, 2021. Any changes to the
KDHE Compliance Schedule (Exhibit E) require KDHE written approval. Additional Notice to
Proceeds will be required for Phase 1 B and Phase 2.
CITY OF SALINA, KANSAS
Owner
Given by:
Authorized Signature
Copy to Engineer
Revised. 1-2-15 NP -1