Change Order #7 City of Salina Approval Level: 0 City Manager 0 Commission CONTRACT CHANGE ORDER Project# 14-1162 Salina Fire Station#1 Change Order#7 Gravity Works Architecture See Attached Narrative Change in Contract Price: Increase $2,000.00 Brief During the design process Gravity Works was asked Justification: to attend various meetings at the City pertaining to items such as zoning regulations, and the subsequent PDD application process. They also provided additional services with respect to the formation and finalization of AIA contract documents. $2,000.00 This Change Order represents full and final settlement for the changes described herein including the architect's expenses and profit. These changes result in the following adjustment of the Contract price. Original Contract Award Value $111,491 Previously Approved Change Orders N/A $6,848 Previously Revised Contract Value $118,339.25 Current Change Order Value $2,000 Revised Contract Value $120,339 This document is a sup. ement to the contract and all provisions will apply hereto ei Requested by: J ' / Date CO 'SO'(6 Gravity W b rks Architecture Reviewed and Recommended by: Date 11-1q-15 Frew Development Group Approved by: .- /i �J Date 4-4-4.a c' Salina Fire Chief Approved by: Date C y Manager GRAVITY::WORKS A R C H I T E C T U R E October 9,2015 Mr.Keith Searcy,Project Manager Frew Development Group, LLC 44 Cook Street,Suite 1000 Denver,CO 80206 RE: Salina Fire Department-Station No. 1 -Phase 11 Mr.Searcy, This letter is in regards to the AIA 8103 Owner/Architect Agreement-specifically as it pertains to reimbursable expenses and the stated limit on the number of site visits during the construction phase. Compensation for Reimbursable Expenses - Section 11.8 The agreement states a not-to-exceed amount of$3,000.0°for reimbursable expenses. This amount was negotiated with Frew Development Group in good faith that the project was ready to begin Preliminary Design and proceed through Construction Phase. During the Preliminary Design process,it was discovered that the project was non- compliant with the zoning regulations,and subsequently,Planned Development District application and site plan review process was required. We do not intend to negotiate additional services for our time involved in this unanticipated process. However,this additional service accounted for three round trips on October 15,2014, December 2,2014,and December22,2014,and printing costs(6/15/2015-$135.00), totaling$477.72 in additional reimbursable expenses. On December 15,2014,Frew Development requested that Gravity Works Architecture generate construction contract agreements. This was recognized as additional service by Frew Development Group and Gravity::Works at the time. This additional service accounted for$260.00. On February 19,2015,and again on March 3,2015,we were asked to attend two meetings in Salina to discuss project scope reduction ahead of the presentation of recommendation to the City Commission. We do not intend to negotiate additional services for our time involved in this unanticipated process. However,this additional 101 S.Star El Dorado, KS 67042 316.321.4774 gravityworks-architecture.com service accounted for two round trips on February 19,2015 and March 3,2015,totaling $234.60 in additional reimbursable expenses. The March 3r°trip has not been invoiced to the City of Salina. Likewise,a trip on January 26,2015(pre-bid conference),and on March 16,2015 have not been invoiced to the City of Salina. A summary of mileage is attached for your review. All trips are listed in the summary,with those yet to be invoiced shown in red. Per your direction,these additional services have been forwarded within the reimbursable expenses. To date we have made twenty-four(24)trips to Salina,all of which were scheduled and endorsed by the City of Salina,and Frew Development. Of these twenty-four(24)trips, ten(10)were completed prior to the construction phase. Additional Services - Section 4.3.3 The agreement,in item 2,authorizes sixteen(16)pre-approved site visits during the construction phase. We have been to the job site fourteen(14)times-twelve(12)of which have been invoiced(excluding 9/14/15&9/28/15 trips)to date. As outlined in the agreement,we are to notify the Owner's Representative when the stated limits are reached,and any additional approved site visits shall be conducted as Additional Service. The stated limit will be reached following the scheduled meeting on October 26,2015. After consultation with the General Contractor,we propose four(4) additional trips will be required during the construction phase,totaling twenty(20). I respectfully request that the stated amount not to exceed for reimbursable expenses be increased by$2,000.°°,going from$3,000.0°up to$5,000.0°. Our current expenses are projected to total$4,915.92. i trust these additions meet with satisfaction. With your approval,I will generate a change order to the B103 Agreement for your signature. Thanks again for your consideration. C d' ll}f, f - 1,1 " Vince Haines,AIA Principal End: Summary of Addt'l Services&Printing,Summary of Mileage Summary of Additional Services & Printing - October 9, 2015 SALINA FIRE STATION NO.1 ADDITIONAL SERVICES 12-15-2014 GENERATE AIA 133 AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER AS CONTRACTOR PRINCIPAL-1 HOUR @$120°°/HR. CLERICAL-3.5 HOURS @$40°°/HR. REQUEST BY FREW SUBTOTAL $260.00 PRINTING LINE ITEM 01-09-2015 INVOICE-SALINA BLUEPRINT-(6)SETS PLANS&SPECS PLAN REVIEW SUBMITTAL SUBTOTAL $1,014.41 PRINTING LINE ITEM 02-02-2015 INVOICE -SALINA BLUEPRINT PLAN REVIEW RESUBMITTAL SUBTOTAL $43.69 PRINTING LINE ITEM 06-15-2015 GRAVITY::WORKS ARCHITECTURE IN HOUSE PRINTING SITE PLAN UPDATES-PDD FOLLOW-UP SUBTOTAL $135.00 Summary of Mileage-October 9, 2015 SAUNA FIRE STATION NO.1 09-30-2014 LIMON-NEWTON,KS TO SALINA,KS TO NEWTON,KS 131 MILES TOTAL TRIP AT$0.56 FED REIMB RATE PROGRAMMING SUBTOTAL $73.36 10-15-2014 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.56 FED REIMB RATE CITY-DESIGN REVIEW TEAM SUBTOTAL $ 114.24 10-23-2014 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.56 FED REIMB RATE SCHEM REVIEW SUBTOTAL $ 114.24 12-2-2014 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.56 FED REIMB RATE PLANNING COMMISSION-PDD SUBTOTAL $114.24 12-22-2014 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.56 FED REIMB RATE CITY COMMISSION-PDD SUBTOTAL $114.24 01-09-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CD REVIEW SUBTOTAL $117.30 01-26-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE PRE-BID CONF SUBTOTAL $ 117.30 02-19-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT 50.575 FED REIMB RATE SCOPE REDUCTION SUBTOTAL $ 117.30 03-03-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE SCOPE REDUCTION SUBTOTAL $117.30 03-16-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT 50.575 FED REIMB RATE CITY COMMISSION SUBTOTAL S 117.30 04-08-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(1/16) SUBTOTAL $ 117.30 04-13-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(2/16) SUBTOTAL $117.30 04-27-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(3/16) SUBTOTAL $ 117.30 05-11-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(4/16) SUBTOTAL $ 117.30 05-26-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(5/16) SUBTOTAL $ 117.30 06-08-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(6/16) SUBTOTAL $ 117.30 06-22-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(7/16) SUBTOTAL $ 117.30 07-06-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTIOIN PHASE(8/16) SUBTOTAL $ 117.30 07-20-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(9/16) SUBTOTAL $ 117.30 08-03-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(10/16) SUBTOTAL $ 117.30 08-17-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(11/16) SUBTOTAL $ 117.30 08-31-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(12/16) SUBTOTAL $ 117.30 09-14-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(13/16) SUBTOTAL $ 117.30 09-28-2015 STEWART-EL DORADO,KS TO SALINA,KS TO EL DORADO,KS 204 MILES TOTAL TRIP AT$0.575 FED REIMB RATE CONSTRUCTION PHASE(14/16) SUBTOTAL 5 117.30