6.3 Awd Johnson Water Main CITY OF SALINA
REQUEST FOR COMMI SS 1 ON ACT ION
DATE
8-1 7-81 '
TIME
4: O0 P .M.
AGENDA SECTION:
NO. 6
CONSENT
ITEM
NO. 3
ORIGINATING DEPARTMENT:
ENGINEERING
BY: Dean BoNer
APPROV ED FOR
~ AGENDA:,
BY:
Bids were received on August 13, 1981 at lO:O0 A.M. for certain
watermain improvements along Coronado Street (Project No. 81-685).
The bids received are tabulated below:
(a) Smoky Hill, Inc.
- $10,111.80
(b) Hagan Bros., Inc.
- $11,520.50
(c) Bud's Plumbing Co.
(d) Wilson Constructors, Inc.
- '$11,897.29
- $11,996.00
.The four (4) bids were then reviewed by our office and all bids
were found to be valid. It is our recommendation that the contract
for the above improvements (Project No. 81-685) be awarded to Smoky
Hill, Inc., Salina, Kansas, who submitted the low bid of $10,111.80.
The Engineer's Estimate for this project was $11,175.00.