mayfair add. wastewater extension 12/5/1989President: ELMER G. ZERR, P.E. P. 0. Drawer M Colby, Kansas 67701 (913) 462-6992 ENGINEERING • SURVEYING • MAPPING • PLANNING December 5, 1989 Donald E. Hoff, City of Salina P.O. Box 736 Salina, Kansas P.E. 67402-0736 RE: Wastewater Collection System Improvements Mayfair Addition Salina, Kansas Project No. 89-099 Dear Don, Vice -President GALEN L. FORGY, R.L.S. 1043 Greeley Salina, Kansas 67401 (913) 827-9710 Please find enclosed a copy of the Application for Sewer Extension Permit for the above referenced project. Please have the same executed by the appropriate city official and forward it to the following address: Mr. Ron Siemens Division of Environment Kansas Dept. of Health & Environment Forbes Field Topeka, Kansas 66620 We would appreciate a copy of the fully executed document for our files. Thank you. Yours truly, Elmer President EGZ/1 Enclosure State of Kansas DIVISION OF ENVIRONMENT APPLICATION FOR SEWER EXTENSION PERMIT The City of Salina hereby makes application for a permit Name o Municipality, Public Sewer District or Person to extend its system of sanitary sewers served by a wastewater treatment facility now operating under Kansas Water Pollution Control Permit No. 0038-474 ,effective July 25 19 86 , in the manner indicated by the plans,specifications, and other data attached hereto. Any municipality, township, county, or legally constituted sewer district, etc., wishing to extend its sanitary sewer system is required by`K.S.A. 65-165 and K.S.A. 65-166 to submit an extension for review by the Division of Environment. Plans and specifications submitted must comply with Division of Environment's "Minimum Standards of Design for Water Pollution 1 What are the conditions and capacity of the existing receiving sewer system: a. Do surcharge or bypass conditions exist in the receiving sewer line(s)?_ If so, what is the location(s)? Rno b. What steps are being taken to eliminate the conditions identified in 1.a.? N/A c. Do bypass conditions exist at downstream receiving pump stations? N/A If so, what is the location? d. What steps are being taken to eliminate the conditions identified in l.c.? N/A e. Are combined sewers used for transporting wastewater flows to the treatment facility? 0761 2. Please provide the following information concerning the waste treatment facility which will receive the flow from the proposed extension: a. What is the present average daily flow at the facility? 3.7 MGD b. Does the facility have a bypass? Yes , Typesvuass Line Estimated frequency of bypass 4 in 10 yrs, Estimated volume of bypass 0.9 MG Average 3. What is the legal name of the addition, subdivision, benefit district., etc., which will be directly served by the sewer extension? Mayfair Addition 4. What is the name and certificate number of the certified operator and the name of the legal jurisdiction which will treat the wastes? George Pauls - Certificate No. 2392 - City of Salina Kansas 5. What are the lengthsand sizes of the sewer line to be built? 1706 LF 8" vCP 6. How many manholes and clean -outs will be built? 18 7. - If wastewater pumping facilities are included in the P P 9 project, provide the following information: ,� a. d: f: 9• 8. Are Are Number of Pumps b. Capacity and Head , c. Type Method of Control , e. Type of Alarm Control Elevations: Low Level Un , High Level On Alarm , Pumps Off Type of a tel—rnative power or bypass prevention provided? any of the proposed sewer lines or other facilities within a floodplain? No any new service connections located in a floodplain? No 9. Provide the following information concerning the estimated use of the proposed extension: a. Per capita design flow 85 gpd. b. Capita per single family dwelling unit 4 Capita per multi -family dwelling unit c. Probable number of single family dwellings connected first year unknown, maximum number 26 , in what time span? 10 Years d. Probable number of multi -family dwellings connected first year None maximum number in what time span? e. Probable number of office or light commercial units connected first year None What overall flow is expected the first year What is the maximum number which may be connected and in what time span What is the maximum flow expected f. Probable number of commercial and industrial plants to be connected None . Please specify for each plant the estimated flow (gpd), pounds of B005 per day, major activity, estimated number of employees and number of shifts (attach separate sheet on these items). 10. Give the name of the firm responsible for engineering ZAF & ASSOCIATES. p.A 11. Who will provide full time engineering observation of the construction? Personnel from ZAF & ASSOCIATES, P.A. Of the building connections? City of Salina Building Tncmrt'n 12. The information contained above is accurate to the best of my knowledge. (Signed) Registered rof si nsl Enqineer Mailing Address: P.O. Drawer M, 1000 E. Fourth Colby, Kansas 67701 In making application for a sewer extension permit, I hereby certify that continuous engineerin observation of the construction of the proposed improvements, including building connections, shall be provided in accordance with Kansas Department of Health and Environment Regulation 28-16-55. (Signed) Mayor or Authorized Member of Governing Body Title: Mavor Mailing Address: sox 736 Salina, Kansas 67402-0736 State of Kansas DIVISION OF ENVIRONMENT APPLICATION FOR SEWER EXTENSION PERMIT The City of Salina hereby makes application for a permit of Municipality, Public Sewer District or Person to extend its system of sanitary sewers served by a wastewater treatment facility now 3perating under Kansas Water Pollution Control Permit No. 0038-474 ,effective July 25 19 86 , in the manner indicated by the plans,specifications, and other data attached hereto. Any municipality, township, county, or legally constituted sewer district, etc., wishing to extend its sanitary sewer system is required by K.S.A. 65-165 and K.S.A. 65-166 to submit an extension for review by the Division of Environment. Plans and specifications submitted must comply with Division of Environment's "Minimum Standards of Design for Water Pollution Control Facilities". 1. What are the conditions and capacity of the existing receiving sewer system: a. Do surcharge or bypass conditions exist in the receiving sewer line(s)? No If so, what is the location(s)? b. What steps are being taken to eliminate the conditions identified in l.a.? N/A c. Do bypass conditions exist at downstream receiving pump stations? N/A If so, what is the location? d. What steps are being taken to eliminate the conditions identified in l.c.? N/A e. Are combined sewers used for transporting wastewater flows to the treatment facility? No 2. Please provide the following information concerning the waste treatment facility which will receive the flow from the proposed extension: a. What is the present average daily flow at the facility? 3.7 MGD b. Does the facility have a bypass? Yes , Type Bypass Line Estimated frequency of bypass 4 in 10 yrs, Estimated volume of bypass 0.9 MG AyFrage 3. What is the legal name of the addition, subdivision, benefit district, etc., which will be directly served by the sewer extension? Mayfair Addition 4. What is the name and certificate number of the certified operator and the name of the legal jurisdiction which will treat the wastes? George Pauls - Certificate No. 2197 - City of Salina Kansas 5. What are the lengthsand sizes of the sewer line to be built? 1706 LF 8" VCP 6. How many manholes and clean -outs will be built? 18 �7. 4f wastewater pumping facilities are included in the project, provide the following information: a. Number of Pumps_. b. Capacity and Head C. Type d: Method of Control e. Type of Alarm f'. Control Elevations: Low Level Tn High Level On , Alarm , Pumps Off g. Type of alter—native power or bypass prevention provided? 8. Are any of the proposed sewer lines or other facilities within a floodplain? No Are any view service connections located in a floodplain? No 9. Provide the following information concerning the estimated use of the proposed extension: a. Per capita design flow 85 gpd. b. Capita per single family dwelling unit 4 Capita per multi -family dwelling unit c. Probable number of single family dwellings connected first year unknown, maximum number 26 , in what time span? 10 years d. Probable number of multi -family dwellings connected first year. None maximum number , in what time span? e. Probable number of office or light commercial units connected first year None What overall flow is expected the first year What is the maximum number, which may be connected and in what time span What is the maximum flow expected f. Probable number of commercial and industrial plants to be connected None Please specify for each plant the estimated flow (gpd), pounds of B005 per day, major activity, estimated number of employees and number of shifts (attach separate sheet on these items). 10. Give the name of the firm responsible for engineering ZAF & ASSOCIATES P A_ 11. Who will provide full time engineering observation of the construction? Personnel from ng connections 12. The information contained above is accurate to the best of my knowledge. (Signed) Mailing Address: P.O. Drawer M 1000 E. Fourth Colby Kansas 67701 In making application for a sewer extension permit, I hereby certify that continuous engineerin observation of the construction of the proposed improvements, including building connections, shall be provided in accordance with Kansas Department of Health and Environment Regulation 28-16-55. / 1 (Signed Title: Mailing Address: sox 736 Salina, Kansas 67402-0736 KANSAS DEPARTMENT OF HEALTH AND ENVIRONMENT DIVISION OF ENVIRONMENT - BUREAU OF WATER FORBES FIELD, BLDG. 740 TOPEKA, KS 66620-0002 913/296-1500 PERMIT NO. 21161 for Approval of Plans and Specifications for Extension of a Sanitary Sewer In accordance with the provision of K.S.A. 65-165 and K.S.A. 65-166 as amended, the Division of Environment has granted approval* to the plans for MAYFAIR ADDITION and hereby grants permission to City of Salina, City Hall, Salina, Kansas 67401 to discharge sewage from sewer extensions serving Mayfair Addition into Salina (Main Plant), and thence treated into Lower Smoky Hill River in compliance with Kansas Water Pollution Control Permit No. M-SH33-1001, effective April 1987. *Subject to the following conditions and requirements: Provide a manhole on Line MA -1 adjacent to Linden Drive. We have noted that the project references approved specifications currently on file with our office entitled: 2AF and Associates Standard Specifications for Sanitary Sewers KDHE #21169. We are returning: Two (2) approved cover sheets. Continuous engineering observation of the construction of the proposed improvements (observation of building sewer connections shall be the responsibility of the owner unless otherwise specified in contract documents), shall be provided in accordance with Kansas Department of Health and Environment Regulation 28-16-55 and as defined in Water Quality Policy Memorandum #2-78, effective January 18, 1978. Notification that the project has been completed in substantial accordance with the approved plans and specifications must be reported to the Division of Environment with the attached form. For the Secretary, Department of Health and Environment. Done at Topeka this 15th day of December, 1989. oe Mester, P.E. Municipal Programs Section Bureau of Water PC: Elmer 2err North Central District 2.0 File Kansas Department of Health & Environment Division of Environment Bureau of Water Protection Forbes Field, Bldg. 740 Topeka, Kansas 66620-7300 ATTN: Municipal Programs Section Re: Sewer Extension for City of Salina - Mayfair Addition Gentlemen: This letter will serve to notify your office that the above referenced project was constructed in accordance with the approved plans and specifications. The project was approved by your office under Sewer Extension Permit No. 21161, issued December 15, 1989. Sincerely yours, PC: