water main break damage arnold/sutherland 8/9/1989L D. M. A. A R C_ H I T E C T eS D o n n i e D. M a r_ r s, A I A A r c h i t e c t, P A. August 9, 1989 Mr. Don Hoff!! Acting City Engineer City of Salina 300 West Ash Salina, Kansas 67401 RE: Manufacturing Incubator Center City water main break Dear Mr. Hoff: Pursuant to our phone conversation this morning, I was following up a meeting that Mr. Bob Albers and I had several month ago with City Engineer Dean Boyer concerning a water main break which occurred last winter adjacent to the above referred building site. The site for this building is on the east side of Arnold Road, directly south to the City water tower at the Airport Industrial Center. The background on this issue is that during a cold spell last winter, the existing city 10" water main ruptured, and flooded the job site. The contractor had the building and loading dock foundations excavated, reinforcing placed and was ready to place concrete in the open excavations. The water from the water main break flooded the site and filling the open excavations with water. This caused the contractor to have to removed his reinforcing, and clean out the excavations of wet soil material. This increased the amount of concrete required. Since the site was rough graded, the road way ditches along Arnold Avenue and Southerland filled with water and dirt which had to be cleaned out. I feel the city is responsible for the cost for this damage to the job site, and not the contractor, because the existing water main was the cities, and the main was not disturbed by the contractor. Had the water main been part of the construction work, or had the contractor disturbed it, the damages would have been the responsibility of the contractor's builders risk insurance. Several months have gone by since Mr. Boyer was made aware of this problem, and since Mr. Boyer did not take care of this matter before he retired, we need your assistance in taking care of this problem as soon as possible. 1 5 7 S o u t h S e v e n t h • S a I i n a, K a n s a s 6 7 4 0 1 P h o n e 9 1 3- 8 2 3- 6 0 0 2 _ F a x 9 1 3 8 2 3- 1 9 9 2 Enclosed for your information is a copy of Bob Albers Construction, Inc.'s letter concerning the cost of the corrective work required. Should you have any questions, please do not hesitate to call. Sincerely, CONSULTING ARCHITECT awrxu-� Donnie D. Marrs, AIA cc: Mr. Tim Rogers Mr. Bob Albers / BOB ALBERS CONSTRUCTION, INC. An Equal Opportunity Employer 1624 EAST CLOVO BOB ALBERS SALINA. KANSAS 67401 A,.. boa. 913.625.6721 Donnie D. Marrs Architect 157 S. 7th Salina, KS. 67401 RE: Salina Airport Authority Incubator Center Dear Don: March 6, 1989 RE: Change Order Request Broken City Pipe Water Main. The following is the cost incured from broken city pipe damages as follows: Extra concrete for footings, loading: dock. Had to muck out 4 c.y. @ $48.00 per c.y. Extra concrete for west wall footings 9 c.y. @ $48.00 yd. Labor 24 hrs @ $18.00 hr. Sump;pump: 20 hrs @ $11.00 hr. (Labor) Backhoe/ man. 4 hrs, @ $60.00 hr. Haul in dirt where line broke 2 loads @ $45.00 per load Spread dirt 545 loader 1 hr. @ $80.00 hr. Move block with 545 loader 1 hr @ $80.00 hr. Clean out footings & clean up rebar on building. 62 hours @ $18.00 fir. Ditch washed full of dirt, clean out ditch & culvert. 545 loader 6 hrs @ $80.00 hr. Clean out pipe, 2 hrs labor @ $18.00 fir. Misc., tools, pickups, etc. Total Cost This Change Order Request. $incerely, BQB ALBERS CQNST. INC. Clive Dunn $ 192.00 432.00 432.00 220.00 240.00 90.00 80.00 80.00 1,116.00 480.00 36.00 200.00 $3,598.00 APPROVED ERING DEP/f.