fema flood study bucher willis ratliff 3/13/1985DEAN BOYER. P. E.
CITY ENGINEER
ENGINEERING DEPARTMENT
.300 WEST ASH STREET
P. O. BOX 746
SAUNA, KANSAS 67401
AREA CODE 913 527-9451
March 13, 1985
Mr. Thomas Darnell
Development Consultants, Inc.
327 South Fifth Street
Salina, Kansas 67401
Re: FEMA Design Criteria
Dear Mr. Darnell:
DONALD E. HOFF. P. E.
ASST. CITY ENGINEER
D. W. BASSETT
TRAFFIC ENGINEER
In reviewing the data furnished our office by Bucher, Willis & Ratliff,
Consulting Engineers, who performed the hydrologic analysis for the FEMA
Flood Study for Salina, the following listed design assumptions were utilized
in this study:
(a) Runoff was based on the maximum 24 hr. storm (100 yr. &
500 yr. frequency).
(b) Rivers and streams were at high stages which prevented
gravity flow at the storage outlets.
(c) Underseepage at the flood control dikes diminished the
available storage volumes of the ponding areas.
(d) The design rainfall (100 yr. or 500 yr. frequency) occurred
after prior rainfall has saturated the soil within the
drainage basin.
(e) The pumps at the ponding areas are not operating.
(f) A volume of runoff (100 yr. or 500 yr. frequency) was
assumed to equal the inches of direct runoff times the
drainage area of the basin.
If you need any additional information concerning the above referenced
flood study, please contact me.
Sincerely,
MEMBER ... KANSAS LEAGUE.OF MUNICIPALITIES - NATIONAL LEAGUE OF CITIES
Don