white-hunsley iron ave. bridgeSUPPLEMENT AGREEMENT FOR ENGINEERING SERVICES A. PROJECT. Iron Avenue Bridge at cut-off channel, Project No. 85 U-0833-01. B. PURPOSE. This supplemental agreement is made necessary due to an un- anticipated change in scope in the original contract signed the 4th day of February, 1983. C. SCOPE. The additional work required made necessary by Kansas Department of Transportation and Federal Highway Administration requirements presented at the field check meeting held on May 19, 1983, are outlined as follows: 1. Redesign structure to eliminate welding on beams and change bridge width to 48' - 0" curb to curb and design as composite with deck. 2. Prepare detailed plans for the proposed revisions, prepare revised quantities, bid tabulation and final cost estimates based on the revised design. 3. Attend additional conferences as required for approval. D. TIME SCHEDULE. Add forty-five (45) calendar days to the original con- tract time to accomplish -,the additional work. E. ADDITIONAL COMPENSATION... The lump sum fee of $13,459.16 will be revised as follows: I. Additional Conferences. Time Partner: 6 hours Sub Total ---------------------------- 2. Re -design. Labor Overhead $14.42 $27.39 ------------------- Partner: 24 hours $14.42 Project Manager: 16 hours $ 8.08 Sub Total --------------------------------------- 3. Plan Preparation. Project Manager: 24 hours $ 8.08 Detailer: 50 hours $ 7.50 Draftsman: 60 hours $ 7.00 Sub Total $27.39 $15.35 $15.35 $14.25 $13.30 Total 250.86 $ 250.86 $1,003.44 374.88 $1,378.32 $ 562.32 1,087.50 1,218.00 $2,867.82 4. Project Supervision. Partner: Sub Total Time Labor Overhead Total 8 hours $14.42 $27.39 334.48 ----------------------------- $ 334.48 TOTAL------------------------------------------------------ $4,831.48 F. OTHER. All other contract items remain consistent with the original contract This Agreement is supplemental to the agreement signed February 4, 1983, by and between the City of Salina, Kansas, and White, Hunsley and Associates, Consulting Engineers and Planners. IN WITNESS WHEREOF, the parties hereto have mutually consented to the terms of this Supplemental Agreements, for�ngineering ervi es And have af- I fixed their hands and seals this Z2& day of . , 19 CITY OF SALINA, KANSAS Title Attest: aL'I te 1, Title WRTI:, HUNSLEY & ASSOCIATES Partner Title WHITE, HUNSLEY ASSOCIATES consulting engineers planners R.R. 4, BOX 26 19131825-4614 SOUTH INDUSTRIAL AREA SALINA, KANSAS 67401 STATEMENT OF CHARGES in favor of WHITE, HUNSLEY & ASSOCIATES Job No. 8304 To: City of Salina City -County Building Salina, Kansas 67401 Attn: Mr. Dean Boyer, City Engineer KENNETH N. WHITE P.E. HARRY L. HUNSLEY P.E. For: Professional services rendered for the Iron Avenue Bridge at Cut-off Channel Project in accordance with Agreement for Engineering Services and Supplement Agreement. Original Agreement: $13,459.16 Supplemental Agreement: 4,831.48 $18,290.64 Contract Amount --------- Percentage Complete (100%) Less Previous Amount Paid TOTAL AMOUNT DUE WHITE, HUNSLEY & ASSOCIATES Submitted by October 12, 1984 Date j Partner $18,290.64 18,290.64 10,901.92 $ 7,388.72 $ 7,388.72 n I L Ni B, a NI °- e00 "-A z; a C:) �a w Q F 14 6 a Vi t9 eo e9 G y a c E" cn a xw FW G W ai ca d a n I L Ni B, 6 y n I L Ni B, INVOICE 0 INVOICE DATE DESCRIPTION ACCT.* AMOUNT CONFIRMING ORDER SERVICES FOR IRON AVE. PRTDOE 29--0576 THE CITY OF SALINA, KANSAS DATE 5/18/83 PURCHASE ORDER CHECK NO. PURCHASE ORDER NO. 09u66 DATE PAID VENDOR NO. 07180 FUND CAPITAL. IMPROVEMENTS VENDOR SHIP TO WHITEr HUNSLEY to ASSOCIATES PDX 26 SALINA KS 67402 INVOICE 0 INVOICE DATE DESCRIPTION ACCT.* AMOUNT CONFIRMING ORDER SERVICES FOR IRON AVE. PRTDOE 29--0576 4,39.64 TOTAL 4#239.64 REQ. NUMBER 2569]. This is your authorization to fill the above order. RETAIN THIS COPY FOR YOUR FILES, and return invoice for items shipped, to the City of Salina, Box 746, Salina, Kansas 67401. NO BACK ORDER, such items Purchasing Agent Director of Finance will be reordered, if needed. VENDOR'S COPY �I PROPOSAL FOR ENGINEERING SERVICES IRON AVENUE BRIDGE AT CUT-OFF CHANNEL PROJECT City of Salina, Kansas WHITE, HUNSLEY & ASSOCIATES consulting engineers & planners January 1983 PROPOSAL A. Project: Replace existing bridge deck and widen bridge to four 12 - foot lanes (52 feet curb to curb) with sidewalks on both sides. B. Purpose: The construction of the proposed improvements requires design and the preparation of construction plans for this proposed project lo- cated on Iron Street at the Smoky Hill River cut-off channel in the eastern part of Salina, Kansas. C. Scope of Services: The Consultant shall perform the following services upon the signing of an Agreement for Engineering Services and a duly authorized.Notice to Proceed issued by the City of Salina. (See Ex- hibit "A" for a detailed breakdown of Scope of Work) 1. Review with the City the specifications and proposed requirements for the project. 2. Perform the necessary field inspection and design surveys required to complete the project (not including metes and bounds surveys for land and rights-of-way), complete the detail design of the project, and prepare detailed plans and prepare quantities, a bid tabulation and final cost estimates based on the final design. 3. He will provide six (6) copies of the plans for use of the City and submittal to the funding and/or approval agencies. 4. Additional copies of the plans will be furnished to the.City for bidding and construction purposes at the actual cost of such copies. Original documents, survey notes and the like, except for those fur- nished to the Engineer by the City, are and shall remain the property of the Engineer. Original tracings shall be furnished to the City as required for Kansas Department of Transportation projects. 5. He shall assist the City when requested in interpreting the con- struction plans and problems or deviations that may occur during the actual construction of the project. 6. .He will be available to furnish engineering advice and consultation necessary to perfect the improvements for a period of one (1) year after the completion of construction at no additional cost to the City. D. Time Schedule: The Consultant, when notified to proceed with the ser- fices defined herein and upon execution by both parties of an agreement shall promptly commence work and shall complete the engineering services specified under Items 1 thru 3 in the Scope of Services within ninety (90) calendar days following the notice to proceed, exclusive of time spent by the City or other agencies for reviewing the plan submittals. Items 4 thru 6 will be furnished upon request. E. Compensation: The compensation for the services rendered shall be lump sum in the amount of $13,459.16, as estimated thus: a. Conferences and review of project with the City. Partner: Project Manager: Sub Total b. Field Surveys. Party Chief: Instrument Man: Rod Man & Chain Man Sub Total c. Design. Partner: Project Manager Sub Total d. Plan Preparation. Project Manager: Detailer: Draftsman: Sub Total e. Project Supervision. Partner: Time Labor 16 hours $14.42 24 hours $ 8.08 40 hours $ 8.08 24 hours $ 7.50 48 hours $ 7.00 44 hours $14.42 56 hours $ 8.08 Overhead $27.39 $15.35 $15:35 $14.25 $13.30 $27.39 $15.35 40 hours $ 8.08 $15.35 80 hours $ 7.50 $14.25 80 hours $ 7.00 $13.30 32 hours $14.42 $27.39 f. Miscellaneous Assistance and Consultation. Partner: 24 hours $14.42 $27.39 TOTAL--------------------------------- ------ Total $ 668.96 562.32 $ 1,231.28 $ 937.20 522.00 974.40 $ 2,433.60 $ 1,839.64 1,312.08 $ 3,151.72 $ 937.20 1,740.00 1,624.00 $ 4,301.20 $ 1,337.92 $ 1,003.44 - $13,459.16 F. Payment to the Consultant for work on this project to be monthly based on submitted percentage of completion minus ten (10) percent retainage. Final payment including retainage to be paid upon com- pletion and acceptance of plans by the City of Salina. G. Estimates of Construction Cost: Construction cost for this project is estimated at approximately $300,000 without benefit of quantities or plans .and specifications on the work. H. Miscellaneous Provisions: Change in Scope. The scope of work described herein shall be subject to modification or supplement upon the written agreement of the con- tracting parties. Any such modifications in the scope of the work shall be incorporated in this contract by supplemental agreement. At the time of such modification of work, equitable adjustment will be made by the parties to the contract. Conference. Representatives of the City may arrange for such confer- ence and visits as may be deemed necessary or desirable during the progress of the work. Termination. The City reserves the right to terminate the contract at any time, upon written notice, in the event the service of the Con- sultant are unsatisfactory, or upon failure to prosecute the work with due diligence or to complete the work within the time limits specified by this agreement; provided, however, that in any.such case the Con- sultant shall be paid the reasonable value of the services rendered up to the time of termination on the basis of the payment provisions of the agreement. Arbitration. 'Arbitration of all questions in dispute under this agree- ment shall be at the choice of either party and the dispute will finally and conclusively be settled by the decision of the arbitrators, one to be appointed by the City, one by the Consultant, and a third to be chosen by the two appointed. In case these three arbitrators thus chosen fail to agree, two additional arbitrators shall be appointed by the presiding judge of the United States Court of Appeals having jurisdiction over the region which includes the City of Salina, Kansas. By the decision of these arbitrators, or by the majority of them, both parties to this agree- ment shall be finally bound. Arbitrators shall be men capable by training and experience to understand and pass upon the problems to be considered. No one shall serve as arbitrator who has had any financial or pecuniary interest with any of the parties or who is or ever has been employed by any of the parties. No arbitrator shall be an advocate for any of the parties. Compensation to each arbitrator shall be the same and shall be paid equally by both parties. All other expenses shall be paid by the party calling for arbitration. 4 - °3 Date Respectfully submitted, WHITE, HUNSLEY & ASSOCIATES Partner I I 3ARIG 0 z 6 F- I I 3ARIG 0 z 6 AGREEMENT FOR ENGINEERING SERVICES THIS AGREEMENT, made thisype_ vLf, 4 f; 3 , by and between the City of Salina, Kansas, hereinafter called the CITY, and White, Hunsley and Associates, Consulting Engineers and Planners, hereinafter called the CONSULTANT, WHEREAS, the CITY intends to redeck and widen the Iron Avenue Bridge over the cut-off channel within the CITY, and WHEREAS, the CONSULTANT agrees to perform the various pro- fessional engineering services required for the proposed improve- ments as outlined and set forth in accordance with the attached Proposal for Engineering Services and Exhibit "A", therefore IN WITNESS, WHEREOF, the parties hereto have mutually con- sented to the terms of the said Proposal for Engineering Services and have affixed their hands and seals this OWNER: CONSULTANT: CITY OF SALINA, KANSAS WHITE, HUNSLEY & ASSOCIATES ATTEST: Title CL4,XA—� -- " Title e Kenneth N. White, P.E. Partner EXHIBIT "A" CITY OF SALINA, KANSAS IRON AVENUE BRIDGE @ CUT-OFF CHANNEL A. Location. Removal of existing bridge deck and widening the Iron Avenue Bridge at the Flood Protection Cut-off Channel to accommodate four full twelve foot traffic lanes, with sidewalks on both sides. B. Funding. KDOT Urban Funds and/or City Funding C. Required. 1. Field Survey 2. Traffic Information 3. Construction Plans 4. Specifications and Contract Documents 5. Construction Staking 6. Inspection Services 7. Plan Review 8. Legal and Publication D. Breakdown of Scope of Work: Description Consultant City of Salina Field Surveys and Data Collection X City Records Identify Utilities X Information Available Traffic Reports and City -Furnished Identify Lane Requirements Information Preliminary Geometric and Criteria Review X X Preliminary Plans X Utility Relocation Review X X Field and Office Review of Preliminary Plan X City - KDOT Final Plan Preparation X Specifications KDOT Standard Special Specifications X Breakdown (Continued) Description Quantities and Construction Estimate Project Review and Approval Legal and Publication Contract Award Construction Staking Inspection Services Consultant City of Salina Ei X City - KDOT X