8.3 CO 2 Underground CableI [ CITY OF SALINA REQUEST FOR COMMISSION ACTION DATE TIME 04/26/99 4:00 P.M. AGENDA SECTION ORIGINATING DEPARTMENT: APPROVED FOR NO. AGENDA: 8 Utilities Department ITEM NO. 3 BY: Don Heft 7'~~ BY: ~~-~ ITEM Approval of Change Order No. 2, Underground Cable Installation Project No. 98-1086. BACKGROUND A contract in the amount of $89,800 was awarded to TBS Construction, Inc. on March 16, 1998 to install underground cable to remote-read approximately 1,200 water meters. The scope of this work included the installation of a small diameter electrical cable from the meter location near the street curb to a receptacle normally mounted on the side of a house. This cable is placed across yards by using a vibratory plow, trenching or boring machines. The Contractor has completed all the work as specified in the original contract. This project was completed in a timely manner and the quality of the installation work was high. Addressing the concerns of the 1,200 property owners affected by this project was not an easy task. Property owners were advised by the Contractor of the nature of the work and a work schedule. The Contractor's public relations effort was outstanding. TBS Construction, Inc.'s bid price was 11% and 28% below the next two (2) bidders at the original project bid opening last March. Based upon their Iow bid prices and superior job performance, we approached TBS to determine if they would agree to perform the 1999 Underground (U/G) Cable Installation Project, involving another 1,200 addresses, at their 1998 contract unit prices. They were receptive to this proposal and could start work by May 1st. RECOMMENDATION We, therefore, recommend the City Commission approve Change Order No. 2, Project No. 98-1086, in an amount not to exceed $90,800 and authorize TBS Construction, Inc., Chanute, Kansas, to install the U/G cable to remote approximately 1,200 additional water meters. CHANGE ORDER LOCATION Salina, Kansas PROJECT NO. 98-1086 PROJECT Underground Cable Installation CHANGE ORDER Two (2) CONTRACTOR TBS Construction, Inc. Box 552, Chanute, Kansas, 66720 THIS AGREEMENT, made and entered into this day of April, 1999, by and between the CITY OF SALINA, KANSAS, Owner, and the above named Contractor, modifies the existing contract dated March 16, 1998, under the above subject, project and project number in the following particulars to wit: 1. The specifications for certain Underground Cable Improvements in the City of Salina, Kansas, dated January 1998, are hereby amended in the following particulars only; all other terms and conditions remain unchanged. (a) The Owner desires to expand the scope of work to include the installation of underground cable to approximately 1200 additional separate addresses not specified in the original contract documents or in Change Order No. 1. (b) The Contractor has expressed a desire to perform this additional work with no increase in unit prices, but with an extension of time to complete the cable installation: (c) This work shall be located in the following additions/subdivisions: Addition to the Grounds of K.W.U. Morningside Bailey Heights Parkview Beverly Manor Pershing Heights Claflin Pleasantview College View Riker Evergreen Park South Park Faith Southview Hageman Park Sunrise Highland Court Woods Johnson CHANGE ORDER PAGE 2 2. The undersigned proposes to furnish all tools, appliances, equipment and labor required to complete the cable installation in a through, workmanlike, and satisfactory manner in accordance with the project specifications and contract documents for the following prices: Item Description Quantity Unit Unit Total No. Price 1 Cable Installation (TypeA) 42,000 LF $1.40 $58,800.00 2 Cable Installation (Type B) 4,000 LF 6.00 24,000.00 3 Cable Installation (Type C) 2,000 LF 4.00 8,000.00 Change Order No. 2 Total $90,800.00 3. Additional time allowed for completion by reason of this change in scope of work shall be days. The completion date of the total project is now 4. All other terms and conditions of the original contract to remain unchanged. OWNER, FIRST PARTY CONTRACTOR, SECOND PARTY THE CITY OF SALINA, KANSAS TBS CONSTRUCTION, INC BY BY Mayor Jay Barnhart President (Office or position of signer) Attest: City Clerk