8.5 Marymount Road Stormwater ImprovementCITY OF SALINA
REQUEST FOR CITY COMMISSION ACTION DATE TIME
10/5/2009 4:00 P.M.
AGENDA SECTION ORIGINATING DEPARTMENT: APPROVED FOR
NO: 8 AGENDA:
DEPARTMENT OF
ITEM
PUBLIC WORKS
NO. 5
BY:
Page 1
BY: Daniel R. Stack
ITEM:
Consideration of an engineering design agreement with RMA Engineering, LLC (RMA) for street and
stormwater improvement construction plans for the intersection of Marymount Road and Glen Avenue,
City Project No. 08-2712.
BACKGROUND:
City staff is currently working on plans to re move and replace aged and rough pavement on
Marymount Road between Iron Avenue and Crawford Street as well as options to realign and add a
sidewalk on the west side. The intersection of Marymount Road and Gl en Avenue is an area
identified as having inadequate drainage and will need a more in depth design to complete the plans
for these improvements. RMA is a small engineering firm bas ed out of Minneapolis, Kansas
specializing in urban storm drainage. The scope of work outlined in the agreement with RMA includes
looking at two options to alleviate street flooding on Marymount as well as design and construction bid
plans to improve the Glen intersection and “sump” area just south of Ruskin Road.
The contract with RMA is written in a “cost plus fixed fee” forma t with an amount not to exceed
$23,400. The “cost” includes all direct payroll, direct non-payroll and overhead (indirect costs). The
“fixed fee” is a lump sum amount to cover any non-reimbursable costs, pre-tax profit and readiness to
serve. The fixed fee does not change regardless of variations in “cost.” The “cost not to exceed” is a
total amount that cannot be exceeded without prior approval. The attached contract also addresses
the scope of work, consultant’s re sponsibilities, City’s responsibilities, time schedule, and general
provisions.
FISCAL NOTE:
This project will be paid for by flood and drainage funds allocated in the 2009 sub-CIP.
COMFORMANCE WITH STRATEGIC PLAN:
Goal 3: The City will provide the highest quality of services, consistent with governing body direction,
available resources and staff commitment to quality.
RECOMMENDED ACTION:
Staff recommends approval of an Engineering Agreement with RMA for an amount not to exceed
$23,400 for street and stormwater improvement construction plans for the intersection of Marymount
Road and Glen Avenue, City Project No. 08-2712.
Enclosures: Location Map
Engineering Agreement
cc: Jason Rourke, P.E., RMA Engineering, LLC