Change Order No. 1
/'
J:..!!
CHANGE ORDER
LOCATION:
PROJECT: CONDUCTOR-IN-DUCT INSTALLATION
PROJECT NO. 08-2711
CHANGE ORDER NO. One (1)
CONTRACTOR: Mid-Kansas Underaround. PO Box 1411. Manhattan. KS. 66505
THIS AGREEMENT, made and entered into this 12th day of September 2008, by and
between the CITY OF SALINA, KANSAS, Owner, and the above named Contractor, modifies the existing
contract dated July 28. 2008 , under the above subject, project and project number in the following
particulars to wit:
1. The specifications and drawings for street improvements in the City of Salina, Kansas, dated
June. 2008, are hereby amended in the following particulars only; all other terms and conditions
remain unchanged.
Item
No. Description
2-1 Decrease Trenching, 37"
3-1 Decrease CID in Trench
4-1 Increase Bore, 1" Diameter
5-1 Increase CID at Pole Bases
8-1 Add Concrete Encasement
Quantity
111
111
261
6
10
Unit
L.F.
L.F.
L.F.
EA.
L.F.
2. The undersigned proposes to furnish all tools, appliances, equipment, materials, and labor required to
complete the construction in a thorough, workmanlike, and satisfactory manner in accordance with
the drawings, specifications, and contract documents, for the following prices.
- 1 -
.
,~.;"l
CHANGE ORDER
PAGE 2 ,"
Item
No. Description
2-1 Decrease Trenching, 37"
3-1 Decrease CID in Trench
4-1 Increase Bore, 1" Diameter
5-1 Increase CID at Pole Bases
8-1 Add Concrete Encasement
Quantity Unit
111 L.F.
111 L.F.
261 L.F.
6 EA.
10 L.F.
Unit Price
$ 1.80
$ .30
$ 8.50
$80.00
$ 5.50
TOTAL
3. The contract time for completion by reason of this change
o
days.
4. All other terms and conditions of the contract to remain unchanged.
OWNER, FIRST PARTY
THE CITY OF SALINA, KANSAS
CONTRACTOR, SECOND PARTY
MID-KANSAS UNDERGROUND
BY:
~~
Cf(y MANAGER -----
4#hlltd
~~
(0 ice or p Ition of signer)
BY:
- 2 -
Total
-$ 199.80
-$ 33.30
$2,218.50
$ 480.00
$ 55.00
$2,520.40