6.3 CO3 WWTP Maint Facility CITY OF SALINA
~OUEST FOR COMMISSION ACTION DATE TIME
07/20/92 4:00 P.M.
AGENDA SECTION: Consent ORIGINATING DEPARTMENT: APPROVED FOR
NO. 6 · · AGENDA:
Water and Wastewater
NO. 3 BY: Don Hof£ BY:
Item
Change Order No. 3 for Project No. 91-842, Maintenance Facility, Wastewater
Treatment Plant No. 1.
Background
After a thorough review, with the contractor and architect, it was determined a
metal purlin support for the batt insulation included in the building design
could be deleted without adversely affecting the function of the building. All
seams in the insulation batts will be taped in lieu of the metal supports.
The attached Change Order No. 3, in the amount of -$111.00, provides details of
the proposed deletion.
Recommendation
It is recommended the City Commission approve Change Order No. 3, in the amount
of -$111.00, deleting a certain item included in the original contract for the
Maintenance Facility (Project No. 91-842) at Wastewater Treatment Plant No. 1.
COMMISSION ACTION
MOTION BY SECOND BY
TO:
CHANGE owner
ARCHITECT
ORDER CONTRACTOR
FIELD
AIA DOCUMENT G701 OtHer
PROJECT: WASTEWATER TREATMENT PLANT NO. I CHANGE ORDER NUMBER: 3
(name, address) Mai ntenance Bui 1 ding ( Project 91-842)
596 N. r~arymount Rd., Salina, Kansas
TO (Contractor)
r-' ~ ARCHITECT'S PROJECT NO: 9104
Lancaster Construction
6708 Randall Rd. CONTRACT FOR: General Construction
Salina, KS 67401
L__ ._.J CONTRACT DATE: January 29, 1992
You are directed to make the followin§ chan§es in this Contract:
Delete hat channel at roof purlins for bart insulation support. Lap joints
shall be taped:
DEDUCT: ..... $ (111.00)
The original Contract Sum was ..................... $ 110,303.00
Net change by previous Change Orders .................. $ ( 8,951.00)
The Contract Sum prior to this Change Order was ............... $ 101,352.00
The Contract Sum will beX~0X:~X~:~ (decreased) ]~X~,~p~Kby this Change Order. . $ ( 111.00)
The new Contract Sum including this Change Order will be ........... $ 101,241.00 .
The Contract Time will be 0r~'X~~s)~X(unchanged) by zero ( 0 ) Days.
The Date of Completion as of the date of this Change Order therefore is 140 days from notice to proceed. .
Architectural Services PLUS, PA Lancaster Construction City of Salina
ARCHITECT OW~ W. Ash '-
P.O. Box 1731 c~)~c~)~dall Rd.
Address Address Address
Salina: K.~ 674(12-]731 SaJ_tna, KS (6-7401 ~ Salina, KS 67401
~. Ker/neqli B~eu~rly, AIA BYKoDer~ Lancaster< fly C~,-ul B:u_gs, ,-myu,
DATL~ June I5, 19E~2 DATE June 15, 1992 DATE
ATTEST: Stephanie Kru~
[uPuty City Clerk
AIA DOCUMENT G701 ° CtIANGE ORDER · APRIl 1970 EDITION · AIA~ "~ 1970 · TIlE ONE PAGE