Loading...
8.4 CO3 Water Tower Painting CITY OF SALINA REOUEST FOR COMMISSION ACTION DATE TIME 5/11/92 q:O0 P.M. AGENDA SECTION: Administration ORIGINATING DEPARTMENT: APPROVED FOR NO. 8 AGENDA: Water & Wastewater ~j~q ITEM NO. 4 BY: Don Hoff BY: In December, 1990, a contract was awarded to Maguire Iron, Inc. to paint five (5) of our elevated water tanks. The Contractor, Maguire Iron, has completed work on the Wyatt Tower, Airport Tower, and the Gold Road Tower. During the sandblasting and cleaning operations on the Airport Tower, several defects were identified that needed corrective action prior to final application of the paint system on this 150,000 gallon tank. These items include the following: (a) Construct access manhole: +$825 (b) Welding plates on roof: +$850 (c) Welding plate over pitted area: +$500 (d) Paint revisions: -$1,000 (e) Removal of external indicator: $200 All of these items are necessary for safety and maintenance considerations. We have reviewed the scope of work to be performed and a change order has been prepared for your consideration. It is our recommendation the City Commission approve Change Order No. 3 (Project No. 90-817) in the amount of $1,375 and authorize the Mayor to execute this change order. Due to peak water usage during the next four (4) months, painting operations have been suspended until September. The remainder of the towers, Key Acres and Sunset, will be painted this fall. COMMISSION ACTION MOTION BY SECOND BY TO: BUCHER, WILLIS & RATLIFF Sheet ,,[ , of ~. Change Order No. Three r3) Date Apr,_' 1 24. 1992 PROJECT P~inr ~ter Towers OWNER City of Salina CONTRACTOR Ma~uire Iron Inc.~ P.O. Box 1446, Sio~g Falls, SD 57]D, DATE OF CONTRACT O~=~mb~r [0, [990 B,W&R JOB NO. ~-~3~ Description of Change The following changes in the Scope of Work shall be made at the Airport Tower. 1. Construct access manhole. 2. Remove cathodic protection rods and weld plates over holes in the roof. 3. Weld ¼" thick plate over 3/16" deep pit area. 4. Paint base of Airport Tower white in lieu of checker board. - 5. Remove water level indicator. °RGE 2 OF 2 REASON FOR CHANGE: 1. Provide better access ~r personnel and bett~r ventilation. 2. Removal of cathodic protection rods leaves holes in the top of the tank. 3. 3/16" deep pits in 14" plate is unacceptable. 4. Checkerboard painting of base of tower not required. 5. Water level indicator not used and interferes with proper sandblasting and painting of tank. CHANGE IN CONTRACT PRICE: 1. Access manhole $ 825.00 2. Cathodic protection holes 850.00 3. !4" plate at pitted area 500.00 4. Paint base of tower white -1,000.00 5. Water level indicator 200.00 TOTAL INCREASE $1,375.00 Original Contract Price $ 333,090.00 Amount of all Previous Change Orders $ ~,40Q.00 Amount this Change Order $ 1,375.00 New Total Contract Price $ 369~865.00 - Receipt of a copy of this Change Order fully executed constitutes a Notice To Proceed with the work des6ribed herein. Ail requirements of the Contract Documents shall apply to the performance of the work. SUBMITTED: CONFIRMED: BUCHERj WILLIS & RATLIFF CONTRACTOR xaguir~ Iro,, Inc. p,O, Box 1446 Sioux F~lls, SD 57101 Date: .~.., v~,.l~qt. Title: OWNER'. ATTEST: By: Dqte: