8.9 CO2 WWTP Improvement CITY OF SALINA REQUEST FOR COMMISSION ACTION DATE TIME 03/22/93 4:00P.M. AGENDA SECTION: Administration ORIGINATING DEPARTMENT: APPROVED FOR NO. AGENDA: 8 Water and Wastewater NO. 9 BY: Don Hoff BY: Item Approval of Change Order No. 2, (Project No. 90-804) Wastewater Treatment Plant No. I Improvements. Background Walters-Morgan Const., Inc., the contractor for this project, has requested consideration of several revisions to the contract documents. These project modifications include the following- (a) Lower the compressive strength requirement of the concrete used for underground electrical ducts: -$2,520.00 (b) Delete the water meter and strainer on the potable waterline- -$857.13 (c) Replace four (4) gate valves at the existing Primary Clarifiers: +$7,637.62 (d) Add 12" base rock at the Waste Activated Sludge (WAS) Storage Building' +$2,684.99 (e) Increase size of electrical wiring at the Grit Removal/Corrosion Control Building to accommodate larger blowers. Also, relocate a motor control center in this building: +$1,240.79 (f) Replace sections of existing 24" clay pipeline with cast iron pipeline at Primary Clarifiers: +$7,779.29 COMMISSION ACTION MOTION BY SECOND BY TO: CITY OF SALINA REQUEST FOR COMMISSION ACT)ON D~.TE TIME 03/22/93.. q:O0 P.M. AGENDA SECT)ON: Administration ORIGINATING DEPARllMENT: APPROVED FOR NO. AGENDA: Water and Wastewater ITEM NO. BY: Don Hoff BY: We have reviewed the proposed modifications and concur with our consultant (Wilson & Co.) the cost adjustment for each of the six (6) proposals listed above fairly addresses the material, labor, equipment, and overhead costs to perform the work as specified. Recommendation It is recommended the City Commission approve Change Order No. 2 (Project No. 90-804) in the net amount of $15,965.56. CC~IMISSION ACTION MOTION BY SECOND BY TO: CHANGE ORDER FRQJECT: Wastewater Treatment Plant'l - . DAT~OPISSUANC~ .3 March 1993 Advanced Treatment OV~ City of Salina, Kansas City/County Building DA~O~~~ 17 ~rch 1992 ~ 300 W. ~h A~) Salina KS 67401 ~,S~~ 90-804 ~~~ Walters-Morgan Construction, Inc. PO Box 1687 ~~ Wilson & Company, Eng. & Archa ~nhattan KS 665~ 631E. Crawford Salina KS 67401 ~~~ Complete Project ~G~'s ~N~ 89-003L You~~~'~~g~~ ~~~ SEE ATTACHED SHEE~ Odg~C0a~P~z $ .11~285~000.00 O~Coa~a~T~ .549 d~ys ~~~ $ 11.,285,000.0Q ~~~ 5~9 d~ys ~~~ $ 11,300,965.56 ~~~ 5~ Wilson & Compan~ City of Salina Walters-Morgan Construction, Inc. CHANGE ORDER NO. 2 Wastewater Treatment Plant 1 Advanced Treatment Salina, Kansas EPA Project No. C20 1231-01 City Project No. 90-804 WCEA File: 89-003L Proposal No. 1: Change 4000 psi =o 2500 psi Concrete for Electrical Ducts. Credit $2,520.00 ~rouosal No. 2: Delete Meter and Strainer on Potable Water Line. Credit $857.13 Proposal No. 3: Replace Valves 20lA, B, C, & D. Additive Cost $7,637.62 - 0 Days Proposal No. 4: Add Base Rock at WAS Storage Building. Additive Cost $2,684.99 - 2 Days Proposal No. 5: Grit/Corrosion Control Building: Relocate MCCF and Increase Wire Size. Additive Cost $1,240.79 - 0 Days ~roposal No, 6: Replace 24-inch VCP with DIP at Existing Primary Clarifiers No. 1 & 2. Additive Cost $7,779.29 0 Days &COMPANY