8.3 CO2 94 Subdiv Ph II CITY OF SALINA REQUEST FOR COMMISSION ACTION 11/7/94 4:00 P.M. AGENDA SECTION: ORIGINATING DEPARTMENT: APPROVED FOR NO. 8 AGENDA: ITEM Engineering BY: Shawn 0'Leary BY: Item Change Order No. 2 for 1994 Subdivision Improvements, Phase II, Project No. 94-898B. Background The project involves utility system (water and sanitary sewer) improvements in four (4) different subdivisions and two city utility improvements throughout Salina. The City Co~¢gdLission approved the contract on May 16, 1994. The contractor, Smoky Hill, LLC completed the project in accordance with the plans and specifications and ahead of schedule. Before the contract can be completed, a change order is necessary to correct the final quantities of contract items to reflect the actual amounts installed. It is normal in a project of this scope to slightly over or under estimate the amounts of bid items actually needed. In this case, the contract overrun of current bid items is $488.43 or 0.3% of the original contract amount of $168,929.85. Also included in this change order are three new items for miscellaneous additional contract items necessary for the completion of the improvements in the subdivisions. Each item has been reviewed by the City Engineer and negotiated with the contractor. The total additional cost of these items is $2,712.00. RECOMMENDATION It is recommended that the City Commission approve Change Order No. 1 for the 1994 Subdivision Improvements,Phase II, Project No. 94- 898B, in the amount of $3,200.43. COMMISSION ACTION MOTION BY SECOND BY THAT: CHANGE ORDER LOCATION: ~QUNTRY OAK ESTATES PROJECT NO. 94-898B PROJECT: 1994 SUBDIVISION IMPROVEMENTS-PHASE II 'CHANGE ORDER NO.TWO (2) CONTRACTOR: .$1~KY HILL, L.L.C., 645 EAST CRAWFORD. SALIN~,.KS 67401 THIS AGREEMENT, made and entered into this 7th day of November , 1994, by and between the CITY OF SALINA, KANSAS, Owner, and the above named Contractor, modifies the existing contract dated May 16, 1994 , under the above subject, project and project number in the following particulars to wit: 1. The specifications and drawings for certain street improvements in the City of Salina, Kansas, dated .April - . 1994 . , are hereby amended in the following particulars only; all other terms and conditions remain unchanged. Item No. Description 15 - 47 Typical minor overruns/underruns of contract items including water pipe and fittings, sewer pipe and fittings, etc. 48 Add removal and replacement of asphalt pavement for construction of utilities in Country Oak Estates. 49 Add removal and replacement of concrete flume in Country Oak Estates. 2. The undersigned proposes to furnish all tools, appliances, equipment, materials, and labor required to complete the construction in a thorough, workmanlike, and satisfactory manner in accordance with the drawings, specifications, and contract documents, for the following prices: CHANGE ORDER PAGE 2 ITEM UNIT NO. DESCRIPTION OUANTITY UNIT PRICE TOT~L 15-47 Combined Overruns/Underruns - - $ 488.43 $ 488.47 (See Final Pay Estimate) 48 Remove & Replace Asphalt Pvmt. 42 S.Y. 41.0O 1,722.00 49 Remove & Replace Conc. Flume 198 S.F. 5.00 990.00 CHANGE ORDER TOTAL: $.. 3. 200.49 3. Additional time for completion by reason of this change 15 days. 4. All other terms and conditions of the contract to remain unchanged. OWNER, FIRST PARTY CONTRACTOR, SECOND PARTY THE CITY OF SALINA, KANSAS S~0KY HILL, L.L.C. BY: BY: MAYOR (Office or position of signer) Attest: CITY CLERK